11259 N GLORIA AVE 91344
Certificate Information: 11259 N GLORIA AVE 91344
- Application / Permit
- 22010-20000-01927
- Plan Check / Job No.
- B22VN05767
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story detached ADU per ordinance 186,481.
- Permit Issued
- Issued on 10/25/2022
- Issuing Office
- Current Status
- CofO Issued on 10/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | HELEN NGUYEN |
| Corrections Issued | 5/26/2022 | HELEN NGUYEN |
| Quality Review Completed | 6/8/2022 | MICHAEL PEREZ |
| Applicant returned to address corrections | 10/5/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/6/2022 | HELEN NGUYEN |
| Plan Check Approved | 10/13/2022 | HELEN NGUYEN |
| Issued | 10/25/2022 | APPLICANT |
| CofO in Progress | 9/27/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 10/3/2024 | DANIEL ORRANTE |
| CofO Issued | 10/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2022 | CHRIS CHAHBAZ |
| Roof/Waste drainage to street | Cleared | 6/9/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 6/29/2022 | CHRIS CHAHBAZ |
| Construction within easement | Cleared | 8/2/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 9/1/2022 | ANTHONY VARGAS |
| GPI Written Notices | Cleared | 10/5/2022 | HELEN NGUYEN |
| Grading Pre-Inspection | Cleared | 10/5/2022 | HELEN NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/5/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/5/2023 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 6/26/2023 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/26/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/19/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/19/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/19/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 10/19/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/19/2023 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 10/19/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/6/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/6/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/6/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 11/6/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/6/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/6/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 11/20/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/7/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/6/2024 | Partial Approval | JACK KARGODORIAN |
| Sewer | 5/6/2024 | Approved | JACK KARGODORIAN |
| Shower Pan | 5/6/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 5/22/2024 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 9/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 9/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 9/11/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/11/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 9/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 9/11/2024 | Approved | JENNIFER RABUCHIN |
| Final | 9/16/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 9/16/2024 | Conditional Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/18/2024 | Approved | JENNIFER RABUCHIN |
| Final | 9/18/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 9/18/2024 | Approved | JENNIFER RABUCHIN |