Excavation/Setback/Form/Re-Bar
|
10/11/2023
|
Corrections Issued
|
JOHN HAYES
|
|
Excavation/Setback/Form/Re-Bar
|
10/17/2023
|
Partial Approval
|
JOHN HAYES
|
|
Underground Mechanical
|
10/17/2023
|
Approved
|
JOHN HAYES
|
|
Footing/Foundation/Slab
|
11/1/2023
|
Conditional Approval
|
MISAEL ESPARZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/28/2023
|
Corrections Issued
|
JENNIFER RABUCHIN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/7/2023
|
Partial Approval
|
CHRISTOPHER ROJAS
|
|
BUILDING-Rough-Frame
|
1/10/2024
|
Corrections Issued
|
JOHN HAYES
|
|
ELECTRICAL-Rough
|
1/10/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/10/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Green Building Rough
|
1/10/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
HVAC-Rough
|
1/10/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
PLUMBING-Rough
|
1/10/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Verify Sprinkler Sign Off
|
1/10/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
ELECTRICAL-Rough
|
1/12/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/12/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
HVAC-Rough
|
1/12/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
PLUMBING-Rough
|
1/12/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
BUILDING-Rough-Frame
|
1/17/2024
|
Partial Approval
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/17/2024
|
Partial Approval
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/12/2024
|
Corrections Issued
|
JOHN HAYES
|
|
Underground Mechanical
|
3/7/2024
|
Partial Approval
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/12/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/13/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/8/2024
|
Corrections Issued
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/10/2024
|
Not Ready for Inspection
|
JOSE AVILA
|
|
BUILDING-Rough-Frame
|
4/12/2024
|
Corrections Issued
|
JOHN HAYES
|
|
ELECTRICAL-Rough
|
4/12/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/12/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Green Building Rough
|
4/12/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
PLUMBING-Rough
|
4/12/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
Verify Sprinkler Sign Off
|
4/12/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
ELECTRICAL-Rough
|
4/22/2024
|
Corrections Issued
|
JOSE AVILA
|
|
PLUMBING-Rough
|
4/22/2024
|
Not Ready for Inspection
|
JOSE AVILA
|
|
BUILDING-Rough-Frame
|
4/29/2024
|
Not Ready for Inspection
|
JOHN HAYES
|
|
ELECTRICAL-Rough
|
4/29/2024
|
Approved
|
JOHN HAYES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/29/2024
|
Partial Approval
|
JOHN HAYES
|
|
Green Building Rough
|
4/29/2024
|
Approved
|
JOHN HAYES
|
|
Rough-Elec/Plmb/HVAC
|
4/29/2024
|
Approved
|
JOHN HAYES
|
|
Verify Sprinkler Sign Off
|
4/29/2024
|
Approved
|
JOHN HAYES
|
|
Interior/Exterior Lathing
|
5/10/2024
|
Partial Approval
|
JOHN HAYES
|
|
Drywall Nailing
|
5/28/2024
|
Corrections Issued
|
ROBERTO PALACIOS-LOPEZ
|
|
BUILDING-Rough-Frame
|
5/30/2024
|
Approved
|
JOSE AVILA
|
|
Insulation
|
6/7/2024
|
Approved
|
JOSE AVILA
|
|
Interior/Exterior Lathing
|
11/6/2024
|
Not Ready for Inspection
|
ROBERTO PALACIOS-LOPEZ
|
|
Drywall Nailing
|
11/13/2024
|
Not Ready for Inspection
|
JOSE AVILA
|
|
ELECTRICAL-Final
|
4/16/2025
|
Not Ready for Inspection
|
ROBERTO PALACIOS-LOPEZ
|
|
PLUMBING-Final
|
4/16/2025
|
Corrections Issued
|
ROBERTO PALACIOS-LOPEZ
|
|
Drywall Nailing
|
4/28/2025
|
Approved
|
ROBERTO PALACIOS-LOPEZ
|
|
ELECTRICAL-Final
|
4/28/2025
|
Not Ready for Inspection
|
ROBERTO PALACIOS-LOPEZ
|
|
Final
|
4/28/2025
|
Not Ready for Inspection
|
ROBERTO PALACIOS-LOPEZ
|
|
Footing/Foundation/Slab
|
4/28/2025
|
Approved
|
ROBERTO PALACIOS-LOPEZ
|
|
Green Building Final
|
4/28/2025
|
Not Ready for Inspection
|
ROBERTO PALACIOS-LOPEZ
|
|
HVAC-Final
|
4/28/2025
|
Not Ready for Inspection
|
ROBERTO PALACIOS-LOPEZ
|
|
PLUMBING-Final
|
4/28/2025
|
Not Ready for Inspection
|
ROBERTO PALACIOS-LOPEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
4/28/2025
|
SGSOV Not Ready
|
ROBERTO PALACIOS-LOPEZ
|
|
Service/Power Release
|
4/28/2025
|
Not Ready for Inspection
|
ROBERTO PALACIOS-LOPEZ
|
|
Smoke Detectors
|
4/28/2025
|
Not Ready for Inspection
|
ROBERTO PALACIOS-LOPEZ
|
|
Final
|
5/9/2025
|
Corrections Issued
|
ROBERTO PALACIOS-LOPEZ
|
|
Green Building Final
|
5/9/2025
|
Corrections Issued
|
ROBERTO PALACIOS-LOPEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
5/9/2025
|
SGSOV Not Ready
|
ROBERTO PALACIOS-LOPEZ
|
|
Service/Power Release
|
5/9/2025
|
Not Ready for Inspection
|
ROBERTO PALACIOS-LOPEZ
|
|
Smoke Detectors
|
5/9/2025
|
Not Ready for Inspection
|
ROBERTO PALACIOS-LOPEZ
|
|
Final
|
5/22/2025
|
Corrections Issued
|
ROBERTO PALACIOS-LOPEZ
|
|
Gas Test
|
5/22/2025
|
Approved
|
ROBERTO PALACIOS-LOPEZ
|
|
Green Building Final
|
5/22/2025
|
Corrections Issued
|
ROBERTO PALACIOS-LOPEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
5/22/2025
|
SGSOV Approved
|
ROBERTO PALACIOS-LOPEZ
|
|
Smoke Detectors
|
5/22/2025
|
Corrections Issued
|
ROBERTO PALACIOS-LOPEZ
|
|
Final
|
7/5/2025
|
Corrections Issued
|
KEVIN BERBERYAN
|
|
Green Building Final
|
7/5/2025
|
Conditional Approval
|
KEVIN BERBERYAN
|
|
Service/Power Release
|
7/5/2025
|
Conditional Approval
|
KEVIN BERBERYAN
|
|
Smoke Detectors
|
7/5/2025
|
Approved
|
KEVIN BERBERYAN
|
|
Final
|
7/10/2025
|
OK to Issue CofO
|
ROBERTO PALACIOS-LOPEZ
|
|
Green Building Final
|
7/10/2025
|
Approved
|
ROBERTO PALACIOS-LOPEZ
|
|
Service/Power Release
|
7/10/2025
|
Approved
|
ROBERTO PALACIOS-LOPEZ
|