5650 N CARTWRIGHT AVE 91601
Certificate Information: 5650 N CARTWRIGHT AVE 91601
- Application / Permit
- 22010-20000-01920
- Plan Check / Job No.
- B22VN05753
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 3-STORY ADU W/ ROOF TOP DECK. PER LAMC 12.22 A.33 (c)-(d) FIRE SPRINKLER NFPA 13D
- Permit Issued
- Issued on 9/7/2023
- Issuing Office
- Current Status
- CofO Issued on 9/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/30/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 5/6/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/6/2022 | APPLICANT |
| Plan Check Approved | 7/28/2023 | MOHAMMAD ESMAILI |
| Issued | 9/7/2023 | APPLICANT |
| CofO in Progress | 9/2/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 9/16/2025 | RUBEN SALAS |
| CofO Issued | 9/16/2025 | RUBEN SALAS |
| Permit Finaled | 9/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2022 | CARLOS AGUILERA |
| Permit | Cleared | 5/19/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/17/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 9/12/2022 | KURT CORRAL |
| Construction near power lines | Cleared | 12/29/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/24/2023 | ERNEST TSE |
| Trees in Parkway | Cleared | 5/2/2023 | ADALBERTO VERA |
| Building over 36-ft | Cleared | 7/28/2023 | CALOSHA APPROVED |
| Roof/Waste drainage to street | Cleared | 7/28/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | 25/8 Acquisition And Development Llc; Lic. No.: 1076786-B | 19360 RINALDI STREET # 147 NORTHRIDGE, CA 91326 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/11/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/17/2023 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 10/17/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 11/1/2023 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/10/2024 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 1/10/2024 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 1/10/2024 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 1/10/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 1/10/2024 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 1/10/2024 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 1/12/2024 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 1/12/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 1/12/2024 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/17/2024 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2024 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2024 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2024 | Not Ready for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 4/12/2024 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 4/12/2024 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 4/12/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 4/12/2024 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 4/12/2024 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 4/22/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 4/22/2024 | Not Ready for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 4/29/2024 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 4/29/2024 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Partial Approval | JOHN HAYES |
| Green Building Rough | 4/29/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 4/29/2024 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 4/29/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 5/10/2024 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 5/28/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/30/2024 | Approved | JOSE AVILA |
| Insulation | 6/7/2024 | Approved | JOSE AVILA |
| Deputy Wood Construction | 3/28/2025 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Final | 4/14/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 4/14/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 4/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 4/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 4/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 4/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 4/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 4/16/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/28/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 4/28/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 4/28/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/28/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 4/28/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 4/28/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 4/28/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 4/28/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/28/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 4/28/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/28/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/8/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 5/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 5/8/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 5/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 5/8/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 5/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/21/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 5/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 7/1/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/1/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/1/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 7/1/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 7/5/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 7/5/2025 | Conditional Approval | KEVIN BERBERYAN |
| Service/Power Release | 7/5/2025 | Conditional Approval | KEVIN BERBERYAN |
| Final | 7/10/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 7/24/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/24/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 9/2/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |