5650 N CARTWRIGHT AVE 91601

Certificate Information: 5650 N CARTWRIGHT AVE 91601

Application / Permit
22010-20000-01920
Plan Check / Job No.
B22VN05753
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 3-STORY ADU W/ ROOF TOP DECK. PER LAMC 12.22 A.33 (c)-(d) FIRE SPRINKLER NFPA 13D
Permit Issued
Issued on 9/7/2023
Issuing Office
Current Status
CofO Issued on 9/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 MOHAMMAD ESMAILI
Corrections Issued 4/30/2022 MOHAMMAD ESMAILI
Quality Review Completed 5/6/2022 OMID HEDAYAT
Building Plans Picked Up 5/6/2022 APPLICANT
Plan Check Approved 7/28/2023 MOHAMMAD ESMAILI
Issued 9/7/2023 APPLICANT
CofO in Progress 9/2/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 9/16/2025 RUBEN SALAS
CofO Issued 9/16/2025 RUBEN SALAS
Permit Finaled 9/16/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/19/2022 CARLOS AGUILERA
Permit Cleared 5/19/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/17/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 8/17/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 9/12/2022 KURT CORRAL
Construction near power lines Cleared 12/29/2022 RIDWAN HARDY
Low Impact Development Cleared 3/24/2023 ERNEST TSE
Trees in Parkway Cleared 5/2/2023 ADALBERTO VERA
Building over 36-ft Cleared 7/28/2023 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 7/28/2023 DAGOVERTO GUERRERO

Contact Information

Contractor 25/8 Acquisition And Development Llc; Lic. No.: 1076786-B 19360 RINALDI STREET # 147      NORTHRIDGE, CA 91326
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/11/2023 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 10/17/2023 Partial Approval JOHN HAYES
Underground Mechanical 10/17/2023 Approved JOHN HAYES
Footing/Foundation/Slab 11/1/2023 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/10/2024 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 1/10/2024 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 1/10/2024 Not Ready for Inspection JOHN HAYES
Green Building Rough 1/10/2024 Not Ready for Inspection JOHN HAYES
HVAC-Rough 1/10/2024 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 1/10/2024 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 1/10/2024 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 1/12/2024 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Not Ready for Inspection JOHN HAYES
HVAC-Rough 1/12/2024 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 1/12/2024 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/17/2024 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/13/2024 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/5/2024 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 4/12/2024 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 4/12/2024 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Not Ready for Inspection JOHN HAYES
Green Building Rough 4/12/2024 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 4/12/2024 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 4/12/2024 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 4/22/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/22/2024 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 4/29/2024 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 4/29/2024 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Partial Approval JOHN HAYES
Green Building Rough 4/29/2024 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 4/29/2024 Approved JOHN HAYES
Verify Sprinkler Sign Off 4/29/2024 Approved JOHN HAYES
Interior/Exterior Lathing 5/10/2024 Partial Approval JOHN HAYES
Drywall Nailing 5/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/30/2024 Approved JOSE AVILA
Insulation 6/7/2024 Approved JOSE AVILA
Deputy Wood Construction 3/28/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Final 4/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 4/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 4/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/16/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/22/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/28/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 4/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 4/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/28/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/8/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 5/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 5/8/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 5/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/8/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 5/8/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/8/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 5/8/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 5/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 5/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 7/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 7/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 7/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 7/5/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 7/5/2025 Conditional Approval KEVIN BERBERYAN
Service/Power Release 7/5/2025 Conditional Approval KEVIN BERBERYAN
Final 7/10/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Final 7/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 7/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 9/2/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ