3987 1/2-3/4 S DALTON AVE 90062

Certificate Information: 3987 1/2-3/4 S DALTON AVE 90062

Application / Permit
22010-20000-01918
Plan Check / Job No.
B22VN05743
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 32'-9" x 33'-6" THREE STORY SINGLE FAMILY DWELLING W/ ATT. ACCESSORY DWELLING UNIT (PER LAMC 12.22 A.33(c) and (e)); NFPA-13D THRU-OUT
Permit Issued
Issued on 8/15/2022
Issuing Office
Current Status
CofO Issued on 8/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 SEAN SHAHMIRI
Corrections Issued 5/5/2022 SEAN SHAHMIRI
Quality Review Completed 5/6/2022 OMID HEDAYAT
Building Plans Picked Up 5/13/2022 APPLICANT
Plan Check Approved 8/4/2022 SEAN SHAHMIRI
Issued 8/15/2022 APPLICANT
CofO in Progress 8/9/2023 SABAS ALONSO
Permit Finaled 8/13/2023 DEROLD HAUFF
CofO Issued 8/13/2023 DEROLD HAUFF
Permit Finaled 8/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/12/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/16/2022 JEANIE LAM
Sewer availability Cleared 5/16/2022 JEANIE LAM
Hydrant and Access approval Cleared 6/21/2022 DWAYNE LAURENT
Low Impact Development Cleared 7/7/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 7/13/2022 DINAH GARIN

Contact Information

Contractor Nfq Builder Inc; Lic. No.: 1067990-B 2110 ARTESIA BLVD #561      REDONDO BEACH, CA 90278
Engineer Desai,, Anil T; Lic. No.: C24653 1530 VIA LOS COYOTES      LA HABRA, CA 90631
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/29/2022 Partial Approval RYAN SALAZAR
Underground Mechanical 9/29/2022 Approved RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 10/7/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 10/7/2022 Approved SABAS ALONSO
Underground Mechanical 10/7/2022 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 10/26/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Partial Approval SABAS ALONSO
Green Building Rough 10/26/2022 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 10/26/2022 Not Ready for Inspection SABAS ALONSO
Wood Frame 10/26/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 11/22/2022 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Approved SABAS ALONSO
PLUMBING-Rough 11/28/2022 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 11/28/2022 Partial Approval SABAS ALONSO
PLUMBING-Rough 12/5/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Partial Approval SABAS ALONSO
PLUMBING-Rough 12/12/2022 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 12/13/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 12/13/2022 Not Ready for Inspection SABAS ALONSO
Green Building Rough 12/13/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 12/13/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 12/13/2022 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 12/15/2022 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 12/19/2022 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 12/19/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 12/23/2022 Approved SABAS ALONSO
HVAC-Rough 12/23/2022 Approved SABAS ALONSO
Shower Pan 12/23/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 12/30/2022 Conditional Approval SABAS ALONSO
Green Building Rough 12/30/2022 Approved SABAS ALONSO
Shower Pan 12/30/2022 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 12/30/2022 Corrections Issued SABAS ALONSO
Shower Pan 1/4/2023 Corrections Issued SABAS ALONSO
Shower Pan 1/5/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 1/5/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 1/24/2023 Approved SABAS ALONSO
Insulation 1/24/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 1/26/2023 Approved ENRIQUE MIRELES
Drywall Nailing 2/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 2/3/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/3/2023 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 2/9/2023 Approved SABAS ALONSO
Underground Mechanical 4/3/2023 Approved SABAS ALONSO
ELECTRICAL-Final 6/26/2023 Corrections Issued SABAS ALONSO
Gas Test 6/26/2023 Not Ready for Inspection SABAS ALONSO
HVAC-Final 6/26/2023 Approved SABAS ALONSO
PLUMBING-Final 6/26/2023 Approved SABAS ALONSO
Service/Power Release 6/26/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 6/29/2023 Approved SABAS ALONSO
Final 6/29/2023 Corrections Issued SABAS ALONSO
Green Building Final 6/29/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 6/29/2023 Approved SABAS ALONSO
ELECTRICAL-Final 7/18/2023 Approved ALIZAH MAYAGOITIA
Gas Test 7/18/2023 Approved ALIZAH MAYAGOITIA
HVAC-Final 7/18/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 7/18/2023 Approved ALIZAH MAYAGOITIA
Service/Power Release 7/18/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 7/20/2023 No Access for Inspection STUART CHAPMAN
Final 7/25/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 7/31/2023 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 7/31/2023 Approved ENRIQUE MIRELES
Sewer 8/3/2023 Approved SABAS ALONSO
Final 8/8/2023 OK to Issue CofO SABAS ALONSO