3400 S GREENWOOD AVE 90066
Certificate Information: 3400 S GREENWOOD AVE 90066
- Application / Permit
- 22010-20000-01900
- Plan Check / Job No.
- B22VN05690
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY 67' X 90'-10" SINGLE FAMILY DWELLING WITH ATTACHED 3 CAR GARAGE AND ROOFTOP DECK ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 4/28/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 5/9/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/10/2022 | APPLICANT |
| Applicant returned to address corrections | 6/1/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 6/23/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 11/7/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 11/10/2022 | APPLICANT |
| CofO in Progress | 8/20/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 8/22/2024 | RICHARD STEINBACH |
| CofO Issued | 8/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2022 | CATHERINE ADROVER |
| Permit | Cleared | 5/3/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 5/3/2022 | CATHERINE ADROVER |
| ZA Case | Cleared | 5/3/2022 | RICHARD REASER |
| Miscellaneous | Cleared | 5/5/2022 | RAYMOND MUGAMBWA |
| Work Adjacent to Public Way | Cleared | 5/7/2022 | SAUL GARCIA |
| Specific Plan | Cleared | 5/9/2022 | VALERIA CEJA |
| Trees in Parkway | Cleared | 5/24/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 5/26/2022 | RUEL COLE |
| Construction near power lines | Cleared | 6/14/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/14/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/26/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/26/2022 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 11/7/2022 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 11/7/2022 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Architect | Hsu,, Peggy P; Lic. No.: C32998 | 3708 BEVERLY RIDGE DR. SHERMAN OAKS, CA 91423 |
| Contractor | Apex Investment Holdings; Lic. No.: 943202-B | 7095 HOLLYWOOD BOULEVARD #1290 LOS ANGELES, CA 90028 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Shotcrete | 4/14/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Shotcrete | 4/17/2023 | Conditional Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 6/9/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/14/2023 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/29/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/17/2023 | Conditional Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 8/7/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/7/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/2/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 1/30/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/30/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 2/6/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/6/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/6/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 2/6/2024 | Approved | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 2/13/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Shower Pan | 2/13/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 2/23/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/1/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 3/1/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 3/1/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/1/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/12/2024 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 4/8/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 4/30/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Gas Test | 5/16/2024 | Approved | JESUS RODRIGUEZ |
| Sewer | 5/16/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Underground Mechanical | 5/16/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/7/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/12/2024 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 6/12/2024 | Approved | JESUS RODRIGUEZ |
| Sewer | 6/12/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| Final | 7/2/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 7/2/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 7/2/2024 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| Final | 7/16/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 7/16/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Not Ready | JESUS RODRIGUEZ |
| PLUMBING-Final | 7/19/2024 | Approved | JESUS RODRIGUEZ |
| Final | 7/26/2024 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/26/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 7/26/2024 | Approved | REGINA MENDEZ |
| Final | 8/19/2024 | OK to Issue CofO | JESUS RODRIGUEZ |