10568 W CUSHDON AVE 90064
Certificate Information: 10568 W CUSHDON AVE 90064
- Application / Permit
- 22010-20000-01860
- Plan Check / Job No.
- B22VN05604
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW DETACHED 1 STORY (15'-0"x14'-0"), 175 SQFT PATIO COVER
- Permit Issued
- Issued on 10/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | PETER MOSESIAN |
| Corrections Issued | 4/24/2022 | PETER MOSESIAN |
| Quality Review Completed | 4/29/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| Applicant returned to address corrections | 8/23/2022 | PETER MOSESIAN |
| Plan Check Approved | 9/21/2022 | PETER MOSESIAN |
| Issued | 10/28/2022 | APPLICANT |
| CofO in Progress | 3/28/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 4/1/2024 | DANIEL ORRANTE |
| CofO Issued | 4/1/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/1/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/2/2022 | CONNIE CHAUV |
| ZI | Cleared | 5/2/2022 | CONNIE CHAUV |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2022 | VLADIMIR ARUTYUNYAN |
| Low Impact Development | Cleared | 6/9/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 8/3/2022 | VLADIMIR ARUTYUNYAN |
| Specific Plan | Cleared | 8/16/2022 | EDUARDO HERMOSO |
| Construction near power lines | Cleared | 9/15/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Refined Home Construction Inc; Lic. No.: 1001310-B | 113 N SAN VICENTE BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/15/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/23/2022 | Approved | CHRISTOPHER WILSON |
| METHANE-Barrier | 12/23/2022 | Approved | CHRISTOPHER WILSON |
| METHANE-Subgrade | 12/23/2022 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 6/16/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 3/22/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 3/22/2024 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Final | 3/22/2024 | Approved | OGANES TARAKHCHYAN |
| METHANE-Rough | 3/22/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/22/2024 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 3/22/2024 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 3/22/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 3/27/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |