10568 W CUSHDON AVE 90064

Certificate Information: 10568 W CUSHDON AVE 90064

Application / Permit
22010-20000-01859
Plan Check / Job No.
B22VN05604
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (39'-6"x59'-8"), 2630 SQFT 2-STORY SINGLE FAMILY DWELLING W/FRONT PORCH (24 SQFT) W/ATTACHED 2 CAR GARAGE (345 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/28/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 PETER MOSESIAN
Corrections Issued 4/24/2022 PETER MOSESIAN
Quality Review Completed 4/29/2022 OMID HEDAYAT
Building Plans Picked Up 5/2/2022 APPLICANT
Applicant returned to address corrections 8/23/2022 PETER MOSESIAN
Plan Check Approved 9/21/2022 PETER MOSESIAN
Issued 10/28/2022 APPLICANT
CofO in Progress 3/28/2024 OGANES TARAKHCHYAN
Permit Finaled 3/29/2024 DANIEL ORRANTE
CofO Issued 3/29/2024 DANIEL ORRANTE
Permit Finaled 3/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/16/2022 LAURINDA MEADE
Specific Plan Cleared 5/16/2022 CONNIE CHAUV
ZI Cleared 5/16/2022 CONNIE CHAUV
Eng Process Fee Ord 176,300 Cleared 5/17/2022 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 5/17/2022 VLADIMIR ARUTYUNYAN
Low Impact Development Cleared 6/7/2022 TA ANH
Roof/Waste drainage to street Cleared 8/3/2022 VLADIMIR ARUTYUNYAN
Specific Plan Cleared 8/16/2022 EDUARDO HERMOSO
Grading Pre-Inspection Cleared 9/21/2022 PETER MOSESIAN

Contact Information

Contractor Refined Home Construction Inc; Lic. No.: 1001310-B 113 N SAN VICENTE BLVD      BEVERLY HILLS, CA 90211
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/8/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/15/2022 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 12/15/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/23/2022 Approved CHRISTOPHER WILSON
METHANE-Barrier 12/23/2022 Approved CHRISTOPHER WILSON
METHANE-Subgrade 12/23/2022 Approved CHRISTOPHER WILSON
Special/Order Compliance 1/11/2023 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/30/2023 Not Ready for Inspection MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 3/3/2023 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 3/23/2023 Approved JEREMY TODD
ELECTRICAL-Rough 4/4/2023 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Rough 4/4/2023 Approved ASHLEY THOMPSON
PLUMBING-Rough 4/4/2023 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 4/10/2023 Approved ASHLEY THOMPSON
Gas Test 4/10/2023 Partial Approval ASHLEY THOMPSON
PLUMBING-Rough 4/10/2023 Approved ASHLEY THOMPSON
Shower Pan 4/26/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 5/2/2023 Partial Approval CLAYTON GRAHAM
Interior/Exterior Lathing 6/16/2023 Approved JAMES CHAVEZ
Insulation 6/23/2023 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 6/28/2023 Not Ready for Inspection CLAYTON GRAHAM
Green Building Rough 6/28/2023 Corrections Issued CLAYTON GRAHAM
METHANE-Rough 6/28/2023 Corrections Issued CLAYTON GRAHAM
Verify Sprinkler Sign Off 6/28/2023 Approved CLAYTON GRAHAM
Insulation 7/3/2023 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 7/6/2023 Approved CLAYTON GRAHAM
Green Building Rough 7/6/2023 Partial Approval CLAYTON GRAHAM
Insulation 7/6/2023 Approved CLAYTON GRAHAM
METHANE-Rough 7/6/2023 Approved CLAYTON GRAHAM
Drywall Nailing 8/3/2023 Approved MICHAEL PELHAM
Green Building Rough 8/3/2023 Approved MICHAEL PELHAM
Special/Order Compliance 8/3/2023 Corrections Issued MICHAEL PELHAM
HVAC-Final 1/10/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 1/16/2024 Corrections Issued CARLOS MATAMOROS
HVAC-Final 1/16/2024 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 1/16/2024 Corrections Issued CARLOS MATAMOROS
Special/Order Compliance 1/16/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 1/19/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Final 1/19/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 1/22/2024 Approved OGANES TARAKHCHYAN
Special/Order Compliance 2/15/2024 Corrections Issued KENNETH NAGLE
Final 3/22/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 3/22/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 3/22/2024 Approved OGANES TARAKHCHYAN
Smoke Detectors 3/22/2024 Approved OGANES TARAKHCHYAN
Final 3/27/2024 OK to Issue CofO OGANES TARAKHCHYAN