Pre-Inspection
|
5/14/2024
|
Approved
|
MEL KHACHATOURIAN
|
|
Excavation/Setback/Form/Re-Bar
|
5/30/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
Pre-Inspection
|
5/30/2024
|
Approved
|
MEL KHACHATOURIAN
|
|
METHANE-Barrier
|
5/31/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
METHANE-Rough
|
5/31/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
METHANE-Subgrade
|
5/31/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
METHANE-Final
|
6/4/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
METHANE-Rough
|
6/6/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
METHANE-Barrier
|
6/7/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
METHANE-Subgrade
|
6/7/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
METHANE-Subgrade
|
6/10/2024
|
Corrections Issued
|
TEMISTOCLES CAAL
|
|
PLUMBING-Rough
|
6/10/2024
|
Corrections Issued
|
TEMISTOCLES CAAL
|
|
METHANE-Subgrade
|
6/11/2024
|
Approved
|
MEL KHACHATOURIAN
|
|
PLUMBING-Rough
|
6/11/2024
|
Partial Approval
|
MEL KHACHATOURIAN
|
|
METHANE-Barrier
|
6/13/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Deputy Methane Barrier
|
6/14/2024
|
Partial Approval
|
SEAN HAUPT
|
|
METHANE-Barrier
|
6/14/2024
|
Approved
|
SEAN HAUPT
|
|
Excavation/Setback/Form/Re-Bar
|
6/18/2024
|
Corrections Issued
|
MEL KHACHATOURIAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2024
|
Corrections Issued
|
MEL KHACHATOURIAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/25/2024
|
Approved
|
MEL KHACHATOURIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/9/2024
|
Corrections Issued
|
SEAN HAUPT
|
|
BUILDING-Rough-Frame
|
7/11/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/11/2024
|
Partial Approval
|
MEL KHACHATOURIAN
|
|
Green Building Rough
|
7/11/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
METHANE-Rough
|
7/11/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
Verify Sprinkler Sign Off
|
7/11/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
Excavation/Setback/Form/Re-Bar
|
7/24/2024
|
Corrections Issued
|
MEL KHACHATOURIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/24/2024
|
Corrections Issued
|
MEL KHACHATOURIAN
|
|
Deputy Drilled-In Anchors
|
7/25/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/26/2024
|
Approved
|
SEAN HAUPT
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/26/2024
|
Approved
|
SEAN HAUPT
|
|
Footing/Foundation/Slab
|
7/26/2024
|
Approved
|
SEAN HAUPT
|
|
Interior/Exterior Lathing
|
7/26/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Interior/Exterior Lathing
|
8/7/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Special/Order Compliance
|
8/7/2024
|
No Access for Inspection
|
DANIEL VERA
|
|
Interior/Exterior Lathing
|
8/9/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
Rough-Elec/Plmb/HVAC
|
8/9/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
Interior/Exterior Lathing
|
8/13/2024
|
Partial Approval
|
DANIEL VERA
|
|
Rough-Elec/Plmb/HVAC
|
8/14/2024
|
Partial Approval
|
MEL KHACHATOURIAN
|
|
HVAC-Rough
|
8/15/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Wood Frame
|
8/15/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Sewer
|
8/19/2024
|
Approved
|
DAVID FEILER
|
|
Underground Mechanical
|
8/19/2024
|
Partial Approval
|
DAVID FEILER
|
|
BUILDING-Rough-Frame
|
8/27/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Green Building Rough
|
8/27/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
HVAC-Rough
|
8/27/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
METHANE-Rough
|
8/27/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Shower Pan
|
8/27/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Verify Sprinkler Sign Off
|
8/27/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Wood Frame
|
8/27/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Rough-Elec/Plmb/HVAC
|
8/29/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Shower Pan
|
8/29/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
BUILDING-Rough-Frame
|
8/30/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Green Building Rough
|
8/30/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
HVAC-Rough
|
8/30/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
METHANE-Rough
|
8/30/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Verify Sprinkler Sign Off
|
8/30/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
Wood Frame
|
8/30/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
BUILDING-Rough-Frame
|
9/3/2024
|
Approved
|
KIRK SANDERS
|
|
ELECTRICAL-Final
|
9/3/2024
|
Corrections Issued
|
KIRK SANDERS
|
|
Green Building Rough
|
9/3/2024
|
Approved
|
KIRK SANDERS
|
|
HVAC-Final
|
9/3/2024
|
Corrections Issued
|
KIRK SANDERS
|
|
METHANE-Rough
|
9/3/2024
|
Approved
|
KIRK SANDERS
|
|
Rough-Elec/Plmb/HVAC
|
9/3/2024
|
Partial Approval
|
KIRK SANDERS
|
|
Shower Pan
|
9/3/2024
|
Not Ready for Inspection
|
KIRK SANDERS
|
|
Verify Sprinkler Sign Off
|
9/3/2024
|
Approved
|
KIRK SANDERS
|
|
Insulation
|
9/12/2024
|
Corrections Issued
|
ARAM AVEDISIAN
|
|
Insulation
|
9/17/2024
|
Approved
|
ARAM AVEDISIAN
|
|
Drywall Nailing
|
9/24/2024
|
Approved
|
SEAN HAUPT
|
|
Shower Pan
|
9/24/2024
|
Approved
|
SEAN HAUPT
|
|
Interior/Exterior Lathing
|
9/27/2024
|
Approved
|
SEAN HAUPT
|
|
ELECTRICAL-Final
|
11/7/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
ELECTRICAL-Final
|
11/8/2024
|
Partial Approval
|
MEL KHACHATOURIAN
|
|
Special/Order Compliance
|
11/8/2024
|
Approved
|
MEL KHACHATOURIAN
|
|
HVAC-Final
|
11/15/2024
|
No Access for Inspection
|
MEL KHACHATOURIAN
|
|
ELECTRICAL-Final
|
11/27/2024
|
Partial Approval
|
MEL KHACHATOURIAN
|
|
Final
|
11/27/2024
|
Corrections Issued
|
MEL KHACHATOURIAN
|
|
Green Building Final
|
11/27/2024
|
Approved
|
MEL KHACHATOURIAN
|
|
HVAC-Final
|
11/27/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
PLUMBING-Final
|
11/27/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
SGSOV-Seismic Gas S/O Valve
|
11/27/2024
|
SGSOV Not Ready
|
MEL KHACHATOURIAN
|
|
Service/Power Release
|
11/27/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
Smoke Detectors
|
11/27/2024
|
Approved
|
MEL KHACHATOURIAN
|
|
Pre-Inspection
|
12/3/2024
|
Partial Inspection
|
ARAM AVEDISIAN
|
|
ELECTRICAL-Final
|
12/5/2024
|
Approved
|
MEL KHACHATOURIAN
|
|
Gas Test
|
12/5/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
HVAC-Final
|
12/5/2024
|
Approved
|
MEL KHACHATOURIAN
|
|
PLUMBING-Final
|
12/5/2024
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
SGSOV-Seismic Gas S/O Valve
|
12/5/2024
|
SGSOV Not Ready
|
MEL KHACHATOURIAN
|
|
SGSOV-Seismic Gas S/O Valve
|
12/13/2024
|
SGSOV Not Ready
|
BOBBY KEY
|
|
Gas Test
|
1/9/2025
|
Approved
|
KEVIN SARGSYAN
|
|
PLUMBING-Final
|
1/9/2025
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
SGSOV-Seismic Gas S/O Valve
|
1/9/2025
|
SGSOV Not Ready
|
KEVIN SARGSYAN
|
|
PLUMBING-Final
|
1/10/2025
|
Approved
|
MEL KHACHATOURIAN
|
|
Special/Order Compliance
|
1/15/2025
|
Not Ready for Inspection
|
MEL KHACHATOURIAN
|
|
Final
|
1/16/2025
|
OK to Issue CofO
|
MEL KHACHATOURIAN
|
|
SGSOV-Seismic Gas S/O Valve
|
1/16/2025
|
SGSOV Approved
|
MEL KHACHATOURIAN
|