8107 N LEMONA AVE 91402
Certificate Information: 8107 N LEMONA AVE 91402
- Application / Permit
- 22010-20000-01844
- Plan Check / Job No.
- B22VN05545
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 19' X 37'-6" IRREGULAR SHAPED DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/3/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | RAPHAEL ROSAS |
| Corrections Issued | 5/23/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 5/31/2022 | STEVEN KIM |
| Applicant returned to address corrections | 10/6/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 2/3/2023 | RAPHAEL ROSAS |
| Issued | 2/3/2023 | APPLICANT |
| CofO in Progress | 8/30/2024 | VINCENT HANLEY |
| Permit Finaled | 9/5/2024 | DANIEL ORRANTE |
| CofO Issued | 9/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/5/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 9/30/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 9/30/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 10/4/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/5/2023 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 7/6/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 7/19/2023 | Approved | DAVID MATSON |
| Footing/Foundation/Slab | 7/19/2023 | Approved | DAVID MATSON |
| Grounding or Bonding | 7/19/2023 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 9/27/2023 | Conditional Approval | DAVID MATSON |
| Gas Test | 10/24/2023 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Corrections Issued | DAVID MATSON |
| PLUMBING-Rough | 12/27/2023 | Approved | DAVID MATSON |
| Sewer | 12/27/2023 | Approved | DAVID MATSON |
| Underground Mechanical | 12/27/2023 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 1/3/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/3/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 1/3/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 1/3/2024 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 1/3/2024 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 1/3/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 1/30/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/6/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/28/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 2/28/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 3/12/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 3/19/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 3/22/2024 | Conditional Approval | DAVID MATSON |
| Interior/Exterior Lathing | 4/4/2024 | Partial Approval | MATTHEW NELSON |
| Gas Test | 5/23/2024 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/23/2024 | Conditional Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/11/2024 | Approved | DAVID MATSON |
| ELECTRICAL-Final | 6/18/2024 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 6/18/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 6/18/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Approved | VINCENT HANLEY |
| Verify Rec and Parks Fee Memo | 7/2/2024 | No Access for Inspection | VINCENT HANLEY |
| Drywall Nailing | 7/25/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/25/2024 | Approved | VINCENT HANLEY |
| Final | 7/25/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 7/25/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 7/25/2024 | Approved | VINCENT HANLEY |
| Service/Power Release | 7/25/2024 | Approved | VINCENT HANLEY |
| Smoke Detectors | 7/25/2024 | Approved | VINCENT HANLEY |
| Verify Rec and Parks Fee Memo | 7/25/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Final | 8/29/2024 | OK to Issue CofO | VINCENT HANLEY |