8107 N LEMONA AVE 91402

Certificate Information: 8107 N LEMONA AVE 91402

Application / Permit
22010-20000-01844
Plan Check / Job No.
B22VN05545
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19' X 37'-6" IRREGULAR SHAPED DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/3/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 RAPHAEL ROSAS
Corrections Issued 5/23/2022 RAPHAEL ROSAS
Quality Review Completed 5/31/2022 STEVEN KIM
Applicant returned to address corrections 10/6/2022 RAPHAEL ROSAS
Plan Check Approved 2/3/2023 RAPHAEL ROSAS
Issued 2/3/2023 APPLICANT
CofO in Progress 8/30/2024 VINCENT HANLEY
Permit Finaled 9/5/2024 DANIEL ORRANTE
CofO Issued 9/5/2024 DANIEL ORRANTE
Permit Finaled 9/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/4/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/5/2022 CARLOS AGUILERA
Sewer availability Cleared 8/5/2022 CARLOS AGUILERA
Construction near power lines Cleared 9/30/2022 RIDWAN HARDY
Low Impact Development Cleared 9/30/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 10/4/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/5/2023 Partial Approval GREGG CUMMINGS
Underground Mechanical 7/6/2023 Not Ready for Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 7/19/2023 Approved DAVID MATSON
Footing/Foundation/Slab 7/19/2023 Approved DAVID MATSON
Grounding or Bonding 7/19/2023 Partial Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 9/27/2023 Conditional Approval DAVID MATSON
Gas Test 10/24/2023 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Corrections Issued DAVID MATSON
PLUMBING-Rough 12/27/2023 Approved DAVID MATSON
Sewer 12/27/2023 Approved DAVID MATSON
Underground Mechanical 12/27/2023 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 1/3/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 1/3/2024 Approved JENNIFER RABUCHIN
Green Building Rough 1/3/2024 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 1/3/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 1/3/2024 Partial Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 1/3/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/30/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 1/30/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/6/2024 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/28/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 2/28/2024 Approved CHRISTOPHER ROJAS
Insulation 3/12/2024 Approved CHRISTOPHER ROJAS
Shower Pan 3/19/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 3/22/2024 Conditional Approval DAVID MATSON
Interior/Exterior Lathing 4/4/2024 Partial Approval MATTHEW NELSON
Gas Test 5/23/2024 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 5/23/2024 Conditional Approval VINCENT HANLEY
Interior/Exterior Lathing 6/11/2024 Approved DAVID MATSON
ELECTRICAL-Final 6/18/2024 Corrections Issued VINCENT HANLEY
HVAC-Final 6/18/2024 Corrections Issued VINCENT HANLEY
PLUMBING-Final 6/18/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Approved VINCENT HANLEY
Verify Rec and Parks Fee Memo 7/2/2024 No Access for Inspection VINCENT HANLEY
Drywall Nailing 7/25/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 7/25/2024 Approved VINCENT HANLEY
Final 7/25/2024 Corrections Issued VINCENT HANLEY
Green Building Final 7/25/2024 Approved VINCENT HANLEY
HVAC-Final 7/25/2024 Approved VINCENT HANLEY
Service/Power Release 7/25/2024 Approved VINCENT HANLEY
Smoke Detectors 7/25/2024 Approved VINCENT HANLEY
Verify Rec and Parks Fee Memo 7/25/2024 Not Ready for Inspection VINCENT HANLEY
Final 8/29/2024 OK to Issue CofO VINCENT HANLEY