1027 N GALLOWAY ST 90272

Certificate Information: 1027 N GALLOWAY ST 90272

Application / Permit
22010-20000-01825
Plan Check / Job No.
B22VN05521
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 77'-0" X 30'-0" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE WITH PATIO & OPEN TRELLIS _ NFPA 13D FIRE SPRINKLERS REQUIRED. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 COLIN LOREDO
Corrections Issued 5/3/2022 COLIN LOREDO
Quality Review Completed 5/4/2022 OMID HEDAYAT
Building Plans Picked Up 5/6/2022 APPLICANT
Plan Check Approved 9/14/2022 DAWN MC NULTY
Issued 9/28/2022 APPLICANT
CofO in Progress 10/3/2024 JESUS RODRIGUEZ
CofO Issued 10/22/2024 RICHARD STEINBACH
Permit Finaled 10/22/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/13/2022 ANTHONY MAINEZ
Permit Cleared 5/13/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 5/16/2022 ANTHONY MAINEZ
Sewer availability Cleared 5/16/2022 ANTHONY MAINEZ
Trees in Parkway Cleared 6/2/2022 ADALBERTO VERA
Low Impact Development Cleared 6/29/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 7/6/2022 ANTHONY MAINEZ
Hydrant and Access approval Cleared 8/22/2022 GILBERT URREA
GPI Written Notices Cleared 9/14/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 9/14/2022 COLIN LOREDO

Contact Information

Contractor Sun Developers Inc; Lic. No.: 865631-B 23371 MULHOLLAND DRIVE 295      WOODLAND HILLS, CA 91364
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/8/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 12/13/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 1/27/2023 Corrections Issued OGANES TARAKHCHYAN
Pre-Inspection 2/10/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 6/28/2023 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 6/29/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 7/5/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 7/5/2023 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 7/6/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 7/19/2023 Approved OGANES TARAKHCHYAN
Sewer 7/25/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Sewer 7/27/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/31/2023 Corrections Issued OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 7/31/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/3/2023 Approved OGANES TARAKHCHYAN
Green Building Rough 8/3/2023 Approved OGANES TARAKHCHYAN
Insulation 8/14/2023 Approved OGANES TARAKHCHYAN
Drywall Nailing 8/22/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Shower Pan 8/22/2023 Approved OGANES TARAKHCHYAN
Drywall Nailing 8/24/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/25/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/27/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Gas Test 6/28/2024 Approved ARAM AVEDISIAN
PLUMBING-Final 6/28/2024 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Approved ARAM AVEDISIAN
HVAC-Final 7/5/2024 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 7/5/2024 Approved EVAN COOPER
HVAC-Final 7/17/2024 Corrections Issued EVAN COOPER
HVAC-Final 8/8/2024 Approved MICHAEL PELHAM
ELECTRICAL-Final 8/15/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 8/21/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 9/12/2024 Approved JESUS RODRIGUEZ
Final 9/12/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 9/12/2024 Approved JESUS RODRIGUEZ
Green Building Final 9/12/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/12/2024 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 9/12/2024 Approved JESUS RODRIGUEZ
Final 10/2/2024 OK to Issue CofO JESUS RODRIGUEZ
Service/Power Release 10/2/2024 Approved JESUS RODRIGUEZ