1027 N GALLOWAY ST 90272
Certificate Information: 1027 N GALLOWAY ST 90272
- Application / Permit
- 22010-20000-01825
- Plan Check / Job No.
- B22VN05521
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 77'-0" X 30'-0" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE WITH PATIO & OPEN TRELLIS _ NFPA 13D FIRE SPRINKLERS REQUIRED. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | COLIN LOREDO |
| Corrections Issued | 5/3/2022 | COLIN LOREDO |
| Quality Review Completed | 5/4/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/6/2022 | APPLICANT |
| Plan Check Approved | 9/14/2022 | DAWN MC NULTY |
| Issued | 9/28/2022 | APPLICANT |
| CofO in Progress | 10/3/2024 | JESUS RODRIGUEZ |
| CofO Issued | 10/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/13/2022 | ANTHONY MAINEZ |
| Permit | Cleared | 5/13/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 5/16/2022 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 6/2/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 6/29/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 7/6/2022 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 8/22/2022 | GILBERT URREA |
| GPI Written Notices | Cleared | 9/14/2022 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 9/14/2022 | COLIN LOREDO |
Contact Information
| Contractor | Sun Developers Inc; Lic. No.: 865631-B | 23371 MULHOLLAND DRIVE 295 WOODLAND HILLS, CA 91364 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/8/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/13/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/27/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Pre-Inspection | 2/10/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/28/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/29/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/5/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/5/2023 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/6/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/19/2023 | Approved | OGANES TARAKHCHYAN |
| Sewer | 7/25/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Sewer | 7/27/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/31/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 7/31/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/3/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 8/3/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 8/14/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/22/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 8/22/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/24/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/25/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/27/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 6/28/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 6/28/2024 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/28/2024 | SGSOV Approved | ARAM AVEDISIAN |
| HVAC-Final | 7/5/2024 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 7/5/2024 | Approved | EVAN COOPER |
| HVAC-Final | 7/17/2024 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 8/8/2024 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 8/15/2024 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 8/21/2024 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 9/12/2024 | Approved | JESUS RODRIGUEZ |
| Final | 9/12/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/12/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 9/12/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 9/12/2024 | Approved | JESUS RODRIGUEZ |
| Final | 10/2/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| Service/Power Release | 10/2/2024 | Approved | JESUS RODRIGUEZ |