10217 N O'MELVENY AVE 91331

Certificate Information: 10217 N O'MELVENY AVE 91331

Application / Permit
22010-20000-01824
Plan Check / Job No.
B22VN05508
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED TWO-STORY 20' X 24' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/29/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2022 APPLICANT
Assigned to Plan Check Engineer 8/23/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 8/25/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 8/26/2022 OMID HEDAYAT
Building Plans Picked Up 8/30/2022 APPLICANT
Applicant returned to address corrections 6/22/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 11/30/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 12/29/2023 SEWADA ZADOORAN MILAGARDI
Issued 12/29/2023 APPLICANT
CofO in Progress 8/15/2024 MICHEL ABAJAN
CofO Issued 9/12/2024 DANIEL ORRANTE
Permit Finaled 9/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/7/2022 CHRIS CHAHBAZ
Roof/Waste drainage to street Cleared 11/7/2022 CHRIS CHAHBAZ
Eng Process Fee Ord 176,300 Cleared 12/21/2022 CHRIS CHAHBAZ
Sewer availability Cleared 12/21/2022 CHRIS CHAHBAZ
Clean Up Green Up Cleared 10/5/2023 STEVEN WECHSLER
Hydrant and Access approval Cleared 11/22/2023 JOHN CONNEALLY
Construction near power lines Cleared 12/20/2023 TINA MIRANDA
Construction within easement Cleared 12/20/2023 TINA MIRANDA

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B 13302 FILMORE ST      PACOIMA, CA 91331
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/18/2024 Approved MICHEL ABAJAN
Footing/Foundation/Slab 1/18/2024 Approved MICHEL ABAJAN
METHANE-Barrier 1/18/2024 Approved MICHEL ABAJAN
METHANE-Subgrade 1/18/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 2/16/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 4/10/2024 Approved MICHEL ABAJAN
Deputy Wood Construction 4/10/2024 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 4/10/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 4/10/2024 Approved MICHEL ABAJAN
HVAC-Rough 4/10/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 4/10/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 4/10/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/23/2024 Approved MICHEL ABAJAN
Insulation 4/25/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/25/2024 Approved MICHEL ABAJAN
Shower Pan 4/25/2024 Approved MICHEL ABAJAN
Drywall Nailing 4/29/2024 Approved MICHEL ABAJAN
Underground Mechanical 6/18/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/6/2024 SGSOV Not Ready MATTHEW NELSON
ELECTRICAL-Final 8/7/2024 Approved MICHEL ABAJAN
Final 8/7/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 8/7/2024 Approved MICHEL ABAJAN
HVAC-Final 8/7/2024 Approved MICHEL ABAJAN
PLUMBING-Final 8/7/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/7/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 8/7/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 8/7/2024 Approved MICHEL ABAJAN
Final 8/15/2024 OK to Issue CofO MICHEL ABAJAN