23730 W HARTLAND ST 91307
Certificate Information: 23730 W HARTLAND ST 91307
- Application / Permit
- 22010-20000-01822
- Plan Check / Job No.
- B22VN05464
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: (N) DETACHED ADU
- Permit Issued
- Issued on 11/30/2022
- Issuing Office
- Current Status
- CofO Issued on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2022 | FERNANDO FLORES |
| Corrections Issued | 5/12/2022 | FERNANDO FLORES |
| Plan Check Approved | 11/9/2022 | FERNANDO FLORES |
| Plan Check Approved | 11/9/2022 | FERNANDO FLORES |
| No Progress | 11/22/2022 | FERNANDO FLORES |
| Issued | 11/30/2022 | APPLICANT |
| CofO in Progress | 8/8/2024 | GEVORK IPCHYAN |
| Permit Finaled | 8/14/2024 | JOHN JANSON |
| CofO Issued | 8/14/2024 | JOHN JANSON |
| Permit Finaled | 8/14/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 8/5/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 11/3/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 11/3/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 11/3/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Hanson Construction; Lic. No.: 518490-B | , |
| Engineer | Lobana,, Singh Maninder Pa; Lic. No.: C50989 | 885 PATRIOT DR #G MOORPARK, CA 93021 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/4/2024 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 1/10/2024 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Approval | TROY SANDERS |
| Green Building Rough | 2/16/2024 | Not Ready for Inspection | TROY SANDERS |
| Sewer | 2/16/2024 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 2/16/2024 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/23/2024 | Partial Approval | TROY SANDERS |
| Green Building Rough | 2/23/2024 | Approved | TROY SANDERS |
| Underground Mechanical | 2/23/2024 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/8/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 3/11/2024 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 3/18/2024 | Approved | TROY SANDERS |
| HVAC-Rough | 3/18/2024 | Approved | TROY SANDERS |
| PLUMBING-Rough | 3/18/2024 | Approved | TROY SANDERS |
| Drywall Nailing | 3/26/2024 | Approved | TROY SANDERS |
| Service/Power Release | 3/26/2024 | Approved | TROY SANDERS |
| Gas Test | 4/30/2024 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 6/6/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 6/6/2024 | Partial Approval | GEVORK IPCHYAN |
| Final | 6/6/2024 | Corrections Issued | GEVORK IPCHYAN |
| Green Building Final | 6/6/2024 | Partial Approval | GEVORK IPCHYAN |
| HVAC-Final | 6/6/2024 | Partial Approval | GEVORK IPCHYAN |
| PLUMBING-Final | 6/6/2024 | Partial Approval | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Not Ready | GEVORK IPCHYAN |
| Smoke Detectors | 6/6/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 6/28/2024 | Approved | GEVORK IPCHYAN |
| Green Building Final | 6/28/2024 | Approved | GEVORK IPCHYAN |
| Grounding or Bonding | 6/28/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 6/28/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 6/28/2024 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Approved | GEVORK IPCHYAN |
| Final | 8/5/2024 | Partial Approval | GEVORK IPCHYAN |
| Final | 8/7/2024 | OK to Issue CofO | GEVORK IPCHYAN |