641 1/2 W 51ST ST 90037
Certificate Information: 641 1/2 W 51ST ST 90037
- Application / Permit
- 22010-20000-01804
- Plan Check / Job No.
- B22VN05424
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER CA GOVT. CODE 65852.2(e)(1)(D) and APPLICABLE PART OF LAMC 12.22.A.33(c)-(d), (g) - (BUILDING-B). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 1/31/2023
- Issuing Office
- Current Status
- Issued on 1/31/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | YOUNG KIM |
| Corrections Issued | 5/2/2022 | YOUNG KIM |
| Quality Review Completed | 6/3/2022 | FARUK SEZER |
| Applicant returned to address corrections | 8/24/2022 | YOUNG KIM |
| Applicant returned to address corrections | 9/29/2022 | YOUNG KIM |
| Applicant returned to address corrections | 11/23/2022 | YOUNG KIM |
| Applicant returned to address corrections | 1/9/2023 | YOUNG KIM |
| Plan Check Approved | 1/13/2023 | YOUNG KIM |
| Issued | 1/31/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 7/15/2022 | AMAAN MALIK |
| Highway dedication | Cleared | 8/25/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 9/27/2022 | AMAAN MALIK |
| Miscellaneous | Cleared | 10/31/2022 | JAZMIN ROQUE |
Contact Information
| Contractor | Swami International Inc; Lic. No.: 833804-B | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 21126 MERRIDY STREET CHATSWORTH, CA 91311 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/13/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 3/13/2023 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 4/3/2023 | Corrections Issued | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 4/6/2023 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 4/18/2023 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 6/2/2023 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 6/2/2023 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 6/21/2023 | Approved | BRENDAN MORELLI |
| Deputy Wood Construction | 6/21/2023 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Approved | BRENDAN MORELLI |
| Rough-Elec/Plmb/HVAC | 6/21/2023 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 6/21/2023 | Approved | BRENDAN MORELLI |
| Insulation | 6/26/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/26/2023 | Approved | STUART CHAPMAN |
| Shower Pan | 6/26/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 7/7/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 10/16/2024 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Final | 10/16/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Final | 10/16/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 12/29/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 12/29/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 3/2/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 3/2/2026 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 3/2/2026 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 3/2/2026 | Approved | BARRY HACHE |
| Final | 3/10/2026 | No Access for Inspection | BARRY HACHE |
| Service/Power Release | 3/10/2026 | No Access for Inspection | BARRY HACHE |
| Deck | 3/23/2026 | Partial Inspection | BARRY HACHE |
| Protected Tree Letter | 3/23/2026 | Partial Inspection | BARRY HACHE |
| ELECTRICAL-Final | 3/25/2026 | Approved | BARRY HACHE |
| Final | 3/25/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 3/25/2026 | Approved | BARRY HACHE |