7720 N INDEPENDENCE AVE 91304
Certificate Information: 7720 N INDEPENDENCE AVE 91304
- Application / Permit
- 22010-20000-01799
- Plan Check / Job No.
- B22VN05417
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21' 6" X 22' 6" DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 8/22/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 5/8/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 5/12/2022 | APPLICANT |
| Plan Check Approved | 8/16/2022 | SERGIO MUNIZ |
| Issued | 8/22/2022 | APPLICANT |
| CofO in Progress | 6/20/2023 | ALEXANDER HANDY |
| Permit Finaled | 7/13/2023 | JOHN JANSON |
| CofO Issued | 7/13/2023 | JOHN JANSON |
| Permit Finaled | 7/13/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 6/13/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/13/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 6/14/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 6/14/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 6/14/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 7/14/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abedian,, Vanik; Lic. No.: S5323 | 2906 JOLLEY DR BURBANK, CA 91504 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/25/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 10/25/2022 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 11/3/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 12/9/2022 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/19/2022 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 1/24/2023 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 1/24/2023 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 1/24/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 1/26/2023 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 2/1/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 2/1/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 2/1/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 2/1/2023 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 2/1/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 4/18/2023 | Approved | ALEXANDER HANDY |
| Final | 4/18/2023 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/18/2023 | SGSOV Approved | ALEXANDER HANDY |
| Final | 6/16/2023 | OK to Issue CofO | ALEXANDER HANDY |
| Footing/Foundation/Slab | 6/16/2023 | Approved | ALEXANDER HANDY |
| Green Building Final | 6/16/2023 | Approved | ALEXANDER HANDY |
| HVAC-Final | 6/16/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 6/16/2023 | Approved | ALEXANDER HANDY |
| Service/Power Release | 6/16/2023 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 6/16/2023 | Approved | ALEXANDER HANDY |