4253 E RAYNOL ST 90032
Certificate Information: 4253 E RAYNOL ST 90032
- Application / Permit
- 22010-20000-01797
- Plan Check / Job No.
- B22VN05411
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 4 STORY SINGLE FAMILY DWELLING W/ATT 2 CAR GARAGE. DECK ON 3RD FLOOR
- Permit Issued
- Issued on 6/7/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | LAMAR DAVIS |
| Corrections Issued | 5/2/2022 | LAMAR DAVIS |
| Quality Review Completed | 5/6/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| Applicant returned to address corrections | 1/18/2023 | MARCELA FRANQUEZ |
| Plan Check Approved | 6/7/2023 | MARCELA FRANQUEZ |
| Issued | 6/7/2023 | APPLICANT |
| CofO in Progress | 7/16/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
| CofO Issued | 7/20/2025 | DEROLD HAUFF |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/5/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 5/5/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 5/5/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 5/5/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2022 | JEANETTE VONG |
| Permit | Cleared | 5/5/2022 | CINDY QI |
| Sewer availability | Cleared | 5/5/2022 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 5/26/2022 | LAURINDA MEADE |
| Trees in Parkway | Cleared | 6/8/2022 | ADALBERTO VERA |
| Disturb/Remove Protected Trees | Cleared | 6/10/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 10/20/2022 | ROBERT HUGHES |
| Grading Pre-Inspection | Cleared | 10/20/2022 | ROBERT HUGHES |
| Low Impact Development | Cleared | 10/27/2022 | DEBORA LEITE |
| BHO/Hillside ordinance | Cleared | 10/31/2022 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 10/31/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 10/31/2022 | WALLIE JONG |
| "D" conditions | Cleared | 11/29/2022 | JASON CHAN |
| "Q" conditions | Cleared | 11/29/2022 | JASON CHAN |
| ZI | Cleared | 11/29/2022 | JASON CHAN |
| Miscellaneous | Cleared | 1/18/2023 | LAMAR DAVIS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alatorre-Y-Barroso,, Alejandro Javier; Lic. No.: C32761 | 7411 FLORENCE AVE DOWNEY, CA 90240 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
| Geologist | Aflakian,, Farzad; Lic. No.: EG2051 | 921 PENDIO IRVINE, CA 92620 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 8/1/2023 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/23/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Masonry | 9/13/2023 | Conditional Approval | OSVALDO PARAMO |
| Reinforced Masonry Frame | 9/14/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Masonry | 9/15/2023 | Conditional Approval | OSVALDO PARAMO |
| Deputy Reinf. Masonry | 9/27/2023 | Approved | OSVALDO PARAMO |
| Reinforced Masonry Frame | 9/27/2023 | Corrections Issued | OSVALDO PARAMO |
| Deputy Reinf. Masonry | 9/28/2023 | Conditional Approval | OSVALDO PARAMO |
| Reinforced Masonry Frame | 10/10/2023 | Corrections Issued | SCOTT FINNILA |
| Deputy Reinf. Masonry | 10/11/2023 | Conditional Approval | OSVALDO PARAMO |
| Reinforced Masonry Frame | 10/13/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Masonry | 10/18/2023 | Conditional Approval | OSVALDO PARAMO |
| Reinforced Masonry Frame | 10/19/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Masonry | 10/20/2023 | Conditional Approval | OSVALDO PARAMO |
| Reinforced Masonry Frame | 10/25/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Masonry | 10/27/2023 | Conditional Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 11/8/2023 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 11/8/2023 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/14/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 7/26/2024 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 7/31/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/31/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/2/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/6/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 8/6/2024 | Partial Inspection | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 8/9/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/9/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 8/9/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2024 | Partial Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/27/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 8/27/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 8/27/2024 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 8/27/2024 | Approved | ROY SPAULDING |
| Insulation | 9/3/2024 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 9/17/2024 | Approved | JOHN QUINTANILLA |
| HVAC-Final | 2/11/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/21/2025 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 3/19/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 3/20/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/18/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/18/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Final | 7/2/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 7/2/2025 | Approved | DAVID WILLIAMS |
| Green Building Final | 7/2/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Approved | DAVID WILLIAMS |
| Service/Power Release | 7/2/2025 | Approved | DAVID WILLIAMS |
| Smoke Detectors | 7/2/2025 | Approved | DAVID WILLIAMS |
| Final | 7/14/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |