4445 N FIRMAMENT AVE 91436

Certificate Information: 4445 N FIRMAMENT AVE 91436

Application / Permit
22010-20000-01795
Plan Check / Job No.
B22VN05407
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
(N) 1-STORY PATIO COVER
Permit Issued
Issued on 10/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 NILOOFAR MEHRAIN
Corrections Issued 5/3/2022 NILOOFAR MEHRAIN
Quality Review Completed 5/10/2022 STEVEN KIM
Building Plans Picked Up 5/12/2022 APPLICANT
Applicant returned to address corrections 10/6/2022 NILOOFAR MEHRAIN
Plan Check Approved 10/27/2022 NILOOFAR MEHRAIN
Issued 10/27/2022 APPLICANT
CofO in Progress 11/3/2023 VINCENT HANLEY
CofO Issued 11/8/2023 JOHN JANSON
Permit Finaled 11/8/2023 JOHN JANSON

Permit Application Clearance Information

GPI Written Notices Cleared 5/2/2022 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 5/2/2022 NILOOFAR MEHRAIN
Eng Process Fee Ord 176,300 Cleared 8/4/2022 CARLOS AGUILERA
Low Impact Development Cleared 9/14/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/19/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/8/2023 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 3/9/2023 Approved VINCENT HANLEY
Special/Order Compliance 3/9/2023 Approved VINCENT HANLEY
Deputy Reinf. Concrete 3/10/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 5/23/2023 Approved JOHN KIDWELL
HVAC-Rough 5/23/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 5/26/2023 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 10/16/2023 Approved SEAN WIRCH
Final 10/16/2023 Not Ready for Inspection SEAN WIRCH
Footing/Foundation/Slab 10/16/2023 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Not Ready SEAN WIRCH
Service/Power Release 10/16/2023 Not Ready for Inspection SEAN WIRCH
Smoke Detectors 10/16/2023 Not Ready for Inspection SEAN WIRCH
Verify Sprinkler Sign Off 10/16/2023 Approved SEAN WIRCH
ELECTRICAL-Final 11/2/2023 Approved VINCENT HANLEY
Final 11/2/2023 OK to Issue CofO VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Approved VINCENT HANLEY
Service/Power Release 11/2/2023 Approved VINCENT HANLEY
Smoke Detectors 11/2/2023 Approved VINCENT HANLEY