4445 N FIRMAMENT AVE 91436
Certificate Information: 4445 N FIRMAMENT AVE 91436
- Application / Permit
- 22010-20000-01795
- Plan Check / Job No.
- B22VN05407
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- (N) 1-STORY PATIO COVER
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/3/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/10/2022 | STEVEN KIM |
| Building Plans Picked Up | 5/12/2022 | APPLICANT |
| Applicant returned to address corrections | 10/6/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 10/27/2022 | NILOOFAR MEHRAIN |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 11/3/2023 | VINCENT HANLEY |
| CofO Issued | 11/8/2023 | JOHN JANSON |
| Permit Finaled | 11/8/2023 | JOHN JANSON |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 5/2/2022 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 5/2/2022 | NILOOFAR MEHRAIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 9/14/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/19/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/8/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 3/9/2023 | Approved | VINCENT HANLEY |
| Special/Order Compliance | 3/9/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 3/10/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/23/2023 | Approved | JOHN KIDWELL |
| HVAC-Rough | 5/23/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/26/2023 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | SEAN WIRCH |
| Final | 10/16/2023 | Not Ready for Inspection | SEAN WIRCH |
| Footing/Foundation/Slab | 10/16/2023 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Not Ready | SEAN WIRCH |
| Service/Power Release | 10/16/2023 | Not Ready for Inspection | SEAN WIRCH |
| Smoke Detectors | 10/16/2023 | Not Ready for Inspection | SEAN WIRCH |
| Verify Sprinkler Sign Off | 10/16/2023 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 11/2/2023 | Approved | VINCENT HANLEY |
| Final | 11/2/2023 | OK to Issue CofO | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/2/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 11/2/2023 | Approved | VINCENT HANLEY |
| Smoke Detectors | 11/2/2023 | Approved | VINCENT HANLEY |