4445 N FIRMAMENT AVE 91436
Certificate Information: 4445 N FIRMAMENT AVE 91436
- Application / Permit
- 22010-20000-01793
- Plan Check / Job No.
- B22VN05407
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED 3-CAR GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 11/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/3/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/10/2022 | STEVEN KIM |
| Building Plans Picked Up | 5/12/2022 | APPLICANT |
| Applicant returned to address corrections | 10/6/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 10/27/2022 | NILOOFAR MEHRAIN |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 10/30/2023 | SEAN WIRCH |
| CofO Issued-Status Void | 11/8/2023 | JOHN JANSON |
| Permit Finaled-Status Void | 11/8/2023 | JOHN JANSON |
| Re-Activate Permit | 11/13/2023 | JOHN JANSON |
| Permit Finaled | 11/13/2023 | JOHN JANSON |
| CofO Corrected | 11/13/2023 | JOHN JANSON |
| Permit Finaled | 11/13/2023 | JOHN JANSON |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 5/2/2022 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 5/2/2022 | NILOOFAR MEHRAIN |
| Address approval | Cleared | 6/2/2022 | CARLOS AGUILERA |
| Permit | Cleared | 6/2/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/6/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 7/19/2022 | LAVEON RIDER |
| Trees in Parkway | Cleared | 7/20/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 9/14/2022 | NILOOFAR MEHRAIN |
| Roof/Waste drainage to street | Cleared | 9/14/2022 | CARLOS AGUILERA |
| Excavation more than 5-ft deep | Cleared | 10/6/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/17/2022 | Approved | VINCENT HANLEY |
| Piling/Pier/Caisson | 11/18/2022 | Approved | VINCENT HANLEY |
| Underground Mechanical | 11/30/2022 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/14/2022 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 12/15/2022 | Conditional Approval | JUSTIN HAWLEY |
| Reinforced Concrete Frame | 12/22/2022 | Partial Approval | VINCENT HANLEY |
| Deputy Other (see comments) | 1/9/2023 | Approved | VINCENT HANLEY |
| Reinforced Masonry Frame | 1/9/2023 | Partial Approval | VINCENT HANLEY |
| Special/Order Compliance | 1/9/2023 | Partial Inspection | JESUS PINEDA |
| Deputy Reinf. Concrete | 1/11/2023 | Approved | VINCENT HANLEY |
| Reinforced Concrete Frame | 1/11/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Other (see comments) | 3/3/2023 | Conditional Approval | JESUS PINEDA |
| Deputy Steel/Welding | 3/3/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/7/2023 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/8/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 3/9/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 3/10/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 5/9/2023 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 5/9/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/23/2023 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 5/23/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/26/2023 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/5/2023 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 6/5/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 6/5/2023 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/5/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Wood Frame | 6/5/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/9/2023 | Approved | VINCENT HANLEY |
| Insulation | 6/15/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/23/2023 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 9/5/2023 | Approved | VINCENT HANLEY |
| Service/Power Release | 9/5/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | SEAN WIRCH |
| Final | 10/16/2023 | Corrections Issued | SEAN WIRCH |
| Green Building Final | 10/16/2023 | Not Ready for Inspection | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Not Ready | SEAN WIRCH |
| Smoke Detectors | 10/16/2023 | Not Ready for Inspection | SEAN WIRCH |
| Verify Sprinkler Sign Off | 10/16/2023 | Approved | SEAN WIRCH |
| Final | 10/30/2023 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 10/30/2023 | Approved | SEAN WIRCH |
| HVAC-Final | 10/30/2023 | Approved | SEAN WIRCH |
| PLUMBING-Final | 10/30/2023 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Approved | SEAN WIRCH |
| Smoke Detectors | 10/30/2023 | Approved | SEAN WIRCH |