13361 W FRIAR ST 91401
Certificate Information: 13361 W FRIAR ST 91401
- Application / Permit
- 22010-20000-01780
- Plan Check / Job No.
- B22VN05359
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW 2 STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) CONVERT EXISTING DETACHED 2 CAR GARAGE INTO A RECREATION ROOM
- Permit Issued
- Issued on 11/14/2022
- Issuing Office
- Current Status
- CofO Issued on 6/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | MONICA RAMIREZ |
| Corrections Issued | 5/27/2022 | MONICA RAMIREZ |
| Quality Review Completed | 6/1/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 8/30/2022 | MONICA RAMIREZ |
| Plan Check Approved | 10/5/2022 | MONICA RAMIREZ |
| Issued | 11/14/2022 | APPLICANT |
| CofO in Progress | 6/12/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 6/18/2025 | RUBEN SALAS |
| CofO Issued | 6/18/2025 | RUBEN SALAS |
| Permit Finaled | 6/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/21/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 8/8/2022 | TINA MIRANDA |
| Construction within easement | Cleared | 8/8/2022 | TINA MIRANDA |
| Low Impact Development | Cleared | 8/8/2022 | TA ANH |
| Permit | Cleared | 9/26/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 9/26/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/15/2024 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 3/20/2024 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 3/27/2024 | Partial Inspection | JOSE AVILA |
| PLUMBING-Rough | 4/2/2024 | Conditional Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 5/8/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 5/15/2024 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 5/15/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 5/17/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Wood Frame | 6/11/2024 | Corrections Issued | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 7/17/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/31/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/31/2024 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 8/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Sewer | 8/29/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 8/29/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 9/9/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/9/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/18/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 9/18/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/18/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 10/7/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Insulation | 10/8/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Insulation | 10/10/2024 | Conditional Approval | GAREN HAYRAPETYAN |
| Drywall Nailing | 10/28/2024 | Approved | GAREN HAYRAPETYAN |
| Final | 1/7/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 1/7/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 1/7/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 4/7/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 4/7/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Final | 6/12/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |