7619 N WILBUR AVE 91335

Certificate Information: 7619 N WILBUR AVE 91335

Application / Permit
22010-20000-01773
Plan Check / Job No.
B22VN05345
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan (N) ACCESORY DWELLING UNIT (1,130 SQ FT) PER LAMC 12.22 A.33(c) AND (d) & (N) REC ROOM (290 SQ FT)
Permit Issued
Issued on 9/29/2022
Issuing Office
Current Status
CofO Issued on 4/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 LAMAR DAVIS
Corrections Issued 5/2/2022 LAMAR DAVIS
Quality Review Completed 5/6/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 7/20/2022 LAMAR DAVIS
Plan Check Approved 7/29/2022 LAMAR DAVIS
Issued 9/29/2022 APPLICANT
CofO in Progress 9/26/2023 JEFFREY BULL
Permit Finaled 4/17/2024 DANIEL ORRANTE
CofO Issued 4/17/2024 DANIEL ORRANTE
Permit Finaled 4/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/4/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/4/2022 MEGAN GODINEZ
Sewer availability Cleared 5/4/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 5/28/2022 GILBERT URREA
Low Impact Development Cleared 6/20/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/29/2022 MEGAN GODINEZ

Contact Information

Contractor Pacan Construction Inc; Lic. No.: 1093791-B 1438 S MAIN ST      SANTA ANA, CA 92707
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/5/2022 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/14/2022 Corrections Issued DAVID SANDOVAL
Sewer 11/2/2022 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Partial Approval JEFFREY BULL
Deputy Wood Construction 11/15/2022 Conditional Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Approved JEFFREY BULL
Footing/Foundation/Slab 11/21/2022 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 2/10/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 2/10/2023 Approved JEFFREY BULL
Final 2/10/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 2/10/2023 Approved JEFFREY BULL
HVAC-Rough 2/10/2023 Approved JEFFREY BULL
PLUMBING-Rough 2/10/2023 Approved JEFFREY BULL
Verify Sprinkler Sign Off 2/10/2023 Approved JEFFREY BULL
Insulation 2/14/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 2/14/2023 Partial Approval JEFFREY BULL
Drywall Nailing 2/27/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 3/22/2023 Approved PETER FOLLING
Shower Pan 3/22/2023 Approved PETER FOLLING
Underground Mechanical 4/27/2023 Approved JEFFREY BULL
Final 6/27/2023 Corrections Issued JEFFREY BULL
Green Building Final 6/27/2023 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Not Ready JEFFREY BULL
Service/Power Release 6/27/2023 Not Ready for Inspection JEFFREY BULL
Smoke Detectors 6/27/2023 Approved JEFFREY BULL
ELECTRICAL-Final 9/25/2023 Approved JEFFREY BULL
Final 9/25/2023 OK to Issue CofO JEFFREY BULL
Green Building Final 9/25/2023 Approved JEFFREY BULL
HVAC-Final 9/25/2023 Approved JEFFREY BULL
PLUMBING-Final 9/25/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Approved JEFFREY BULL
Service/Power Release 9/25/2023 Approved JEFFREY BULL
Service/Power Release 11/13/2023 Approved SEAN WIRCH
Service/Power Release 11/14/2023 Not Ready for Inspection JEFFREY BULL