13315 W REEDLEY ST 91402

Certificate Information: 13315 W REEDLEY ST 91402

Application / Permit
22010-20000-01755
Plan Check / Job No.
B22VN05302
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30' X 40' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP 2020. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 6/8/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2022 APPLICANT
Assigned to Plan Check Engineer 4/18/2022 OMAR GARNICA
Corrections Issued 4/19/2022 OMAR GARNICA
Applicant returned to address corrections 6/2/2022 OMAR GARNICA
Plan Check Approved 6/8/2022 OMAR GARNICA
Issued 6/8/2022 APPLICANT
Building Plans Picked Up 6/9/2022 APPLICANT
CofO in Progress 4/28/2023 GREGG CUMMINGS
Permit Finaled 5/2/2023 MICHAEL SMITH
CofO Issued 5/2/2023 MICHAEL SMITH
Permit Finaled 5/2/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/24/2022 CHRIS CHAHBAZ
Roof/Waste drainage to street Cleared 5/24/2022 CHRIS CHAHBAZ
Eng Process Fee Ord 176,300 Cleared 5/25/2022 CHRIS CHAHBAZ
Sewer availability Cleared 5/25/2022 CHRIS CHAHBAZ

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B 13302 FILMORE ST      PACOIMA, CA 91331

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/29/2022 Partial Approval GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 8/3/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 8/3/2022 Approved GREGG CUMMINGS
ELECTRICAL-Rough 9/20/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Partial Approval GREGG CUMMINGS
HVAC-Rough 9/20/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 9/20/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 9/26/2022 Corrections Issued GREGG CUMMINGS
HVAC-Rough 9/26/2022 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 10/3/2022 Approved DEANDRE HOFFMAN
HVAC-Rough 10/3/2022 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 10/6/2022 Approved WILLIAM WREN
Green Building Rough 10/6/2022 Approved WILLIAM WREN
Insulation 10/6/2022 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 10/6/2022 Not Ready for Inspection WILLIAM WREN
Verify Sprinkler Sign Off 10/6/2022 Approved WILLIAM WREN
Insulation 10/7/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 10/7/2022 Partial Approval GREGG CUMMINGS
Drywall Nailing 10/14/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 10/14/2022 Approved WILLIAM WREN
Shower Pan 10/14/2022 Corrections Issued WILLIAM WREN
Shower Pan 11/1/2022 Not Ready for Inspection GREGG CUMMINGS
Shower Pan 11/8/2022 Approved CHRISTOPHER DELLEFIELD
Sewer 12/7/2022 Approved GREGG CUMMINGS
Underground Mechanical 12/7/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 4/12/2023 SGSOV Not Ready GREGG CUMMINGS
Final 4/17/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 4/17/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 4/17/2023 SGSOV Approved GREGG CUMMINGS
Service/Power Release 4/17/2023 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 4/17/2023 Approved GREGG CUMMINGS
Final 4/21/2023 Not Ready for Inspection GREGG CUMMINGS
Service/Power Release 4/21/2023 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 4/27/2023 Approved GREGG CUMMINGS
Final 4/27/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 4/27/2023 Approved GREGG CUMMINGS
PLUMBING-Final 4/27/2023 Approved GREGG CUMMINGS
Service/Power Release 4/27/2023 Approved GREGG CUMMINGS