3659 W VALLEYBRINK ROAD 90039
Certificate Information: 3659 W VALLEYBRINK ROAD 90039
- Application / Permit
- 22010-20000-01737
- Plan Check / Job No.
- B22VN05177
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTION AND ADDITION TO (E) 1 STORY GARAGE TO NEW 2 STORY ACCESSORY DWELLING PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/11/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 5/18/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/19/2022 | APPLICANT |
| Applicant returned to address corrections | 12/7/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 12/21/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 2/1/2023 | MOHAMMAD ESMAILI |
| Issued | 2/17/2023 | APPLICANT |
| CofO in Progress | 12/4/2023 | HAMIK HARTOUNIAN |
| CofO Issued | 12/5/2023 | DEROLD HAUFF |
| Permit Finaled | 12/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/31/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 5/31/2022 | STEVE MELGAR |
| ZI | Cleared | 5/31/2022 | KENTON TRINH |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 6/6/2022 | STEVE MELGAR |
| Construction within easement | Cleared | 8/4/2022 | RIDWAN HARDY |
Contact Information
| Contractor | De Artola Construction; Lic. No.: 593704-B | P O BOX 1711 ARCADIA, CA 91007 |
| Engineer | Banda,, Peter Hector; Lic. No.: C31433 | 1930 W GLENOAKS BLVD STE 07 GLENDALE, CA 91201 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/23/2023 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/2/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/7/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 6/14/2023 | Conditional Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 6/28/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/28/2023 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/28/2023 | Approved | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 6/30/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2023 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/24/2023 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/24/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 7/24/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/8/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/8/2023 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 9/12/2023 | Conditional Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 9/13/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 9/13/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/13/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/19/2023 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 9/19/2023 | Approved | JOSH MEISTER |
| Shower Pan | 9/19/2023 | Approved | JOSH MEISTER |
| Drywall Nailing | 9/28/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/28/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 11/13/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 11/13/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 11/13/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 11/13/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 11/13/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/13/2023 | SGSOV Gas Company | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/13/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 11/30/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 11/30/2023 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/30/2023 | Approved | HAMIK HARTOUNIAN |