3659 W VALLEYBRINK ROAD 90039

Certificate Information: 3659 W VALLEYBRINK ROAD 90039

Application / Permit
22010-20000-01737
Plan Check / Job No.
B22VN05177
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTION AND ADDITION TO (E) 1 STORY GARAGE TO NEW 2 STORY ACCESSORY DWELLING PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 2/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 MOHAMMAD ESMAILI
Corrections Issued 5/11/2022 MOHAMMAD ESMAILI
Quality Review Completed 5/18/2022 OMID HEDAYAT
Building Plans Picked Up 5/19/2022 APPLICANT
Applicant returned to address corrections 12/7/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 12/21/2022 MOHAMMAD ESMAILI
Plan Check Approved 2/1/2023 MOHAMMAD ESMAILI
Issued 2/17/2023 APPLICANT
CofO in Progress 12/4/2023 HAMIK HARTOUNIAN
CofO Issued 12/5/2023 DEROLD HAUFF
Permit Finaled 12/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/31/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 5/31/2022 STEVE MELGAR
ZI Cleared 5/31/2022 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 6/6/2022 STEVE MELGAR
Sewer availability Cleared 6/6/2022 STEVE MELGAR
Construction within easement Cleared 8/4/2022 RIDWAN HARDY

Contact Information

Contractor De Artola Construction; Lic. No.: 593704-B P O BOX 1711      ARCADIA, CA 91007
Engineer Banda,, Peter Hector; Lic. No.: C31433 1930 W GLENOAKS BLVD STE 07      GLENDALE, CA 91201

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/23/2023 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/2/2023 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/7/2023 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 6/14/2023 Conditional Approval RUBEN SALAS
ELECTRICAL-Rough 6/28/2023 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/28/2023 Approved HAMIK HARTOUNIAN
Underground Mechanical 6/28/2023 Approved HAMIK HARTOUNIAN
Deputy Reinf. Concrete 6/30/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/24/2023 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 7/24/2023 Partial Inspection HAMIK HARTOUNIAN
Underground Mechanical 7/24/2023 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/8/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 9/8/2023 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 9/12/2023 Conditional Approval BRENDAN MORELLI
BUILDING-Rough-Frame 9/13/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 9/13/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 9/13/2023 Approved HAMIK HARTOUNIAN
Insulation 9/19/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 9/19/2023 Approved JOSH MEISTER
Shower Pan 9/19/2023 Approved JOSH MEISTER
Drywall Nailing 9/28/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/28/2023 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 11/13/2023 Approved HAMIK HARTOUNIAN
Final 11/13/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 11/13/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 11/13/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Final 11/13/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Gas Company HAMIK HARTOUNIAN
Smoke Detectors 11/13/2023 Corrections Issued HAMIK HARTOUNIAN
Final 11/30/2023 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 11/30/2023 Approved HAMIK HARTOUNIAN
Smoke Detectors 11/30/2023 Approved HAMIK HARTOUNIAN