6254 N MARY ELLEN AVE 91401

Certificate Information: 6254 N MARY ELLEN AVE 91401

Application / Permit
22010-20000-01726
Plan Check / Job No.
B22VN05164
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' X 30' 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 RAPHAEL ROSAS
Corrections Issued 5/18/2022 RAPHAEL ROSAS
Quality Review Completed 5/24/2022 STEVEN KIM
Building Plans Picked Up 5/24/2022 APPLICANT
Applicant returned to address corrections 11/7/2022 RAPHAEL ROSAS
Plan Check Approved 11/21/2022 RAPHAEL ROSAS
Issued 12/23/2022 APPLICANT
CofO in Progress 5/10/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 6/12/2024 RUBEN SALAS
CofO Issued 6/12/2024 RUBEN SALAS
Permit Finaled 6/12/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/1/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 10/18/2022 ROMAN GUTIERREZ
Sewer availability Cleared 10/18/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 10/24/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 10/25/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/28/2022 Approved KIRK SANDERS
PLUMBING-Rough 1/13/2023 Partial Approval MISAEL ESPARZA
Sewer 1/13/2023 Corrections Issued MISAEL ESPARZA
Sewer 1/18/2023 Partial Approval KIRK SANDERS
Excavation/Setback/Form/Re-Bar 1/24/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 1/24/2023 Approved KIRK SANDERS
Underground Mechanical 1/24/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/9/2023 Corrections Issued KIRK SANDERS
Green Building Rough 2/9/2023 Not Ready for Inspection KIRK SANDERS
Verify Sprinkler Sign Off 2/9/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/28/2023 Corrections Issued JAVIER RAMOS JR
Special/Order Compliance 2/28/2023 Corrections Issued JAVIER RAMOS JR
Verify Sprinkler Sign Off 2/28/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/4/2023 Partial Approval KIRK SANDERS
HVAC-Rough 5/4/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 5/4/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 5/11/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 5/11/2023 Corrections Issued KIRK SANDERS
Green Building Rough 5/11/2023 Approved KIRK SANDERS
HVAC-Rough 5/11/2023 Conditional Approval KIRK SANDERS
PLUMBING-Rough 5/11/2023 Approved KIRK SANDERS
Verify Sprinkler Sign Off 5/11/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/30/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 5/30/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Approved KIRK SANDERS
HVAC-Rough 5/30/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 5/30/2023 Partial Approval KIRK SANDERS
Insulation 6/8/2023 Approved RYAN SALAZAR
Drywall Nailing 6/21/2023 Approved ROBERT GOLD
Interior/Exterior Lathing 6/21/2023 Approved ROBERT GOLD
Shower Pan 6/21/2023 Approved ROBERT GOLD
Sewer 10/10/2023 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 3/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 3/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 3/28/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 3/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 3/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 3/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/28/2024 Approved ROBERTO PALACIOS-LOPEZ
Gas Test 4/1/2024 Approved JOSE AVILA
ELECTRICAL-Final 4/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 4/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/16/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 5/10/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ