4256 N CAMELLIA AVE 91604
Certificate Information: 4256 N CAMELLIA AVE 91604
- Application / Permit
- 22010-20000-01703
- Plan Check / Job No.
- B22VN05073
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 38' X 57'-8" IRREGULAR SHAPED 2-STORY SFD W/ 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 5/16/2024
- Issuing Office
- Current Status
- Issued on 5/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
Submitted | 4/6/2022 | APPLICANT |
Assigned to Plan Check Engineer | 5/5/2022 | RAPHAEL ROSAS |
Corrections Issued | 5/16/2022 | RAPHAEL ROSAS |
Quality Review Completed | 5/24/2022 | STEVEN KIM |
Building Plans Picked Up | 5/24/2022 | APPLICANT |
Applicant returned to address corrections | 9/26/2022 | RAPHAEL ROSAS |
Applicant returned to address corrections | 12/13/2023 | RAPHAEL ROSAS |
Plan Check Approved | 12/19/2023 | RAPHAEL ROSAS |
Issued | 5/16/2024 | APPLICANT |
Permit Application Clearance Information
Address approval | Cleared | 5/20/2022 | LEE GUILBEAUX |
Permit | Cleared | 5/20/2022 | LEE GUILBEAUX |
Eng Process Fee Ord 176,300 | Cleared | 5/24/2022 | LEE GUILBEAUX |
Sewer availability | Cleared | 5/24/2022 | LEE GUILBEAUX |
ZI | Cleared | 6/7/2022 | NELSON RODRIGUEZ |
Hydrant and Access approval | Cleared | 6/24/2022 | KURT CORRAL |
Low Impact Development | Cleared | 12/5/2022 | ERNEST TSE |
Roof/Waste drainage to street | Cleared | 12/5/2022 | LEE GUILBEAUX |
Trees in Parkway | Cleared | 1/10/2023 | ADALBERTO VERA |
Contact Information
Contractor | B M R Enterprises; Lic. No.: 901546-B | 5250 LANKERSHIM BLVD STE 500 LOS ANGELES, CA 91601 |
Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
DANIEL ORRANTE, (818) 374-1157 | Office Hours: 7:00-8:00 AM MON-FRI |
JUAN VALENZUELA, (818) 374-1157 | Office Hours: 7:00-8:00 AM MON-FRI |
MICHAEL CORTEZ, (818) 374-1157 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
Interior/Exterior Lathing | 5/8/2025 Time Frame: 2-4 |
Wood Frame | 5/8/2025 Time Frame: 2-4 |
Inspection Request History
Excavation/Setback/Form/Re-Bar | 6/25/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
Underground Mechanical | 6/25/2024 | Corrections Issued | CHRISTOPHER ROJAS |
Footing/Foundation/Slab | 6/27/2024 | Partial Approval | CHRISTOPHER ROJAS |
PLUMBING-Rough | 6/27/2024 | Approved | CHRISTOPHER ROJAS |
Footing/Foundation/Slab | 7/1/2024 | Approved | CHRISTOPHER ROJAS |
Deputy Reinf. Concrete | 7/2/2024 | Conditional Approval | JUAN VALENZUELA |
Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
BUILDING-Rough-Frame | 8/1/2024 | Corrections Issued | ROBERT GOLD |
Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Partial Approval | ROBERT GOLD |
Green Building Rough | 8/1/2024 | Not Ready for Inspection | ROBERT GOLD |
Verify Sprinkler Sign Off | 8/1/2024 | Not Ready for Inspection | ROBERT GOLD |
Floor/Roof Diaphrgm/Shear Wall | 8/6/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
Pre-Inspection | 8/9/2024 | Partial Approval | CHRISTOPHER ROJAS |
BUILDING-Rough-Frame | 8/23/2024 | Corrections Issued | CHRISTOPHER ROJAS |
Deputy Wood Construction | 8/23/2024 | Conditional Approval | JUAN VALENZUELA |
Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
Wood Frame | 10/3/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
Pre-Inspection | 10/4/2024 | Partial Inspection | JUAN VALENZUELA |
Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Approved | CHRISTOPHER ROJAS |
BUILDING-Rough-Frame | 11/13/2024 | Corrections Issued | CHRISTOPHER ROJAS |
Gas Test | 11/13/2024 | Partial Inspection | CHRISTOPHER ROJAS |
HVAC-Rough | 11/18/2024 | Not Ready for Inspection | DAVID MATSON |
HVAC-Rough | 11/19/2024 | Corrections Issued | CHRISTOPHER ROJAS |
Interior/Exterior Lathing | 11/19/2024 | Partial Approval | CHRISTOPHER ROJAS |
PLUMBING-Rough | 11/20/2024 | Approved | CHRISTOPHER ROJAS |
ELECTRICAL-Rough | 11/25/2024 | Approved | CHRISTOPHER ROJAS |
BUILDING-Rough-Frame | 12/17/2024 | No Access for Inspection | RAUL OLAGI |
Green Building Rough | 12/17/2024 | No Access for Inspection | RAUL OLAGI |
Verify Sprinkler Sign Off | 12/17/2024 | No Access for Inspection | RAUL OLAGI |
BUILDING-Rough-Frame | 12/20/2024 | Corrections Issued | CHRISTOPHER ROJAS |
HVAC-Rough | 12/20/2024 | Partial Inspection | CHRISTOPHER ROJAS |
Wood Frame | 1/8/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
BUILDING-Rough-Frame | 2/4/2025 | Corrections Issued | CHRISTOPHER ROJAS |
Special/Order Compliance | 2/4/2025 | Order to Comply Issued | JUAN VALENZUELA |
Order to Comply | 3/3/2025 | OTC Issued | JUAN VALENZUELA |
BUILDING-Rough-Frame | 3/6/2025 | Not Ready for Inspection | JUAN VALENZUELA |
Green Building Rough | 3/6/2025 | Not Ready for Inspection | JUAN VALENZUELA |
Insulation | 3/6/2025 | Not Ready for Inspection | JUAN VALENZUELA |
Verify Sprinkler Sign Off | 3/6/2025 | Not Ready for Inspection | JUAN VALENZUELA |
Pre-Inspection | 3/11/2025 | Not Ready for Inspection | JUAN VALENZUELA |
BUILDING-Rough-Frame | 4/22/2025 | Approved | JUAN VALENZUELA |
Green Building Rough | 4/22/2025 | Approved | JUAN VALENZUELA |
Insulation | 4/22/2025 | Approved | JUAN VALENZUELA |
Verify Sprinkler Sign Off | 4/22/2025 | Approved | JUAN VALENZUELA |
Drywall Nailing | 4/29/2025 | Approved | JUAN VALENZUELA |
Green Building Rough | 4/29/2025 | Approved | JUAN VALENZUELA |
Interior/Exterior Lathing | 4/29/2025 | Not Ready for Inspection | JUAN VALENZUELA |