8815 W SAWYER ST 90035

Certificate Information: 8815 W SAWYER ST 90035

Application / Permit
22010-20000-01657
Plan Check / Job No.
B22VN04985
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30'9" X 33'1" 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) AND (d) WITH ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 2/16/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 COLIN LOREDO
Corrections Issued 5/5/2022 COLIN LOREDO
Quality Review Completed 5/10/2022 OMID HEDAYAT
Building Plans Picked Up 5/11/2022 APPLICANT
Applicant returned to address corrections 1/20/2023 MARVEL DELACRUZ
Plan Check Approved 2/3/2023 MARVEL DELACRUZ
Issued 2/16/2023 APPLICANT
CofO in Progress 7/22/2024 MEL KHACHATOURIAN
Permit Finaled 7/24/2024 DANIEL ORRANTE
CofO Issued 7/24/2024 DANIEL ORRANTE
Permit Finaled 7/24/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/16/2022 CELINA MORENO
Construction near power lines Cleared 7/8/2022 TINA MIRANDA
Sewer availability Cleared 10/6/2022 CELINA MORENO
Permit Cleared 10/13/2022 CELINA MORENO
Low Impact Development Cleared 11/9/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 11/10/2022 CELINA MORENO
Hydrant and Access approval Cleared 11/25/2022 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 1/4/2023 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/24/2023 Not Ready for Inspection JEREMY TODD
METHANE-Barrier 5/24/2023 Not Ready for Inspection JEREMY TODD
METHANE-Subgrade 5/24/2023 Not Ready for Inspection JEREMY TODD
Footing/Foundation/Slab 6/13/2023 Partial Approval JEREMY TODD
METHANE-Barrier 6/13/2023 Not Ready for Inspection JEREMY TODD
METHANE-Subgrade 6/13/2023 Approved JEREMY TODD
Footing/Foundation/Slab 6/20/2023 Approved JEREMY TODD
METHANE-Barrier 6/20/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 7/3/2023 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Corrections Issued ARAM AVEDISIAN
Insulation 7/3/2023 Partial Approval ARAM AVEDISIAN
Deputy Wood Construction 7/6/2023 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Partial Approval ARAM AVEDISIAN
Sewer 8/7/2023 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 9/1/2023 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 9/1/2023 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 9/1/2023 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 9/26/2023 Approved MEL KHACHATOURIAN
HVAC-Rough 9/26/2023 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 9/26/2023 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 9/26/2023 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 9/28/2023 Approved BEN MOLSTAD
Green Building Rough 9/28/2023 Approved BEN MOLSTAD
METHANE-Rough 9/28/2023 Approved BEN MOLSTAD
Verify Sprinkler Sign Off 9/28/2023 Approved BEN MOLSTAD
Wood Frame 9/28/2023 Approved BEN MOLSTAD
Insulation 10/18/2023 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 10/18/2023 Not Ready for Inspection MEL KHACHATOURIAN
Drywall Nailing 10/31/2023 Approved MICHAEL PELHAM
Special/Order Compliance 10/31/2023 Corrections Issued MICHAEL PELHAM
Gas Test 12/8/2023 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 12/8/2023 Approved MEL KHACHATOURIAN
Underground Mechanical 12/8/2023 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Final 7/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
Final 7/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Final 7/11/2024 No Access for Inspection MEL KHACHATOURIAN
HVAC-Final 7/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Final 7/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Not Ready MEL KHACHATOURIAN
Service/Power Release 7/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 7/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
Final 7/19/2024 Corrections Issued MEL KHACHATOURIAN
Green Building Final 7/19/2024 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 7/19/2024 SGSOV Approved MEL KHACHATOURIAN
Service/Power Release 7/19/2024 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 7/19/2024 Approved MEL KHACHATOURIAN
Final 7/23/2024 OK to Issue CofO MEL KHACHATOURIAN
Service/Power Release 7/23/2024 Approved MEL KHACHATOURIAN