1042 N EL PASO DR 90042

Certificate Information: 1042 N EL PASO DR 90042

Application / Permit
22010-20000-01655
Plan Check / Job No.
B22VN04980
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT ( 48'-0"X26'-0" ) PER LAMC 12.22 A.33(c) and (d) FIRE SPRINKLER NFPA 13R
Permit Issued
Issued on 5/15/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 MOHAMMAD ESMAILI
Corrections Issued 5/6/2022 MOHAMMAD ESMAILI
Quality Review Completed 5/6/2022 OMID HEDAYAT
Building Plans Picked Up 5/10/2022 APPLICANT
Applicant returned to address corrections 4/14/2023 MOHAMMAD ESMAILI
Plan Check Approved 5/3/2023 MOHAMMAD ESMAILI
Issued 5/15/2023 APPLICANT
CofO in Progress 7/1/2024 SCOTT FINNILA
CofO Issued 7/3/2024 DEROLD HAUFF
Permit Finaled 7/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/5/2022 MOHAMMAD ESMAILI
Address approval Cleared 5/27/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 5/31/2022 CINDY QI
Sewer availability Cleared 5/31/2022 CINDY QI
Hydrant and Access approval Cleared 6/29/2022 KURT CORRAL
Low Impact Development Cleared 8/17/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/22/2022 CINDY QI
GPI Written Notices Cleared 5/3/2023 MOHAMMAD ESMAILI
Grading Preinspection Not Cleared 9/5/2023 Department of Building and Safety
Grading Preinspection Not Cleared 6/28/2024 Department of Building and Safety
Grading Preinspection Not Cleared 6/28/2024 Department of Building and Safety
Grading Preinspection Not Cleared 6/28/2024 Department of Building and Safety
Grading Preinspection Not Cleared 6/28/2024 Department of Building and Safety
Grading Preinspection Not Cleared 6/28/2024 Department of Building and Safety

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/12/2023 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 6/12/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 6/16/2023 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/22/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/10/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 7/10/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Wood Frame 7/10/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 7/19/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 7/19/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/7/2023 Partial Approval ALIZAH MAYAGOITIA
Sewer 8/7/2023 Approved ALIZAH MAYAGOITIA
Underground Mechanical 8/7/2023 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/7/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 9/7/2023 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/18/2023 Conditional Approval BRIAN SULLIVAN
PLUMBING-Rough 9/18/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 10/6/2023 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 10/6/2023 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 10/6/2023 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 10/18/2023 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/18/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 10/18/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/7/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 11/7/2023 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/27/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 11/27/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 11/27/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/13/2023 Approved RICHARD DOCKUS
Insulation 12/13/2023 Approved RICHARD DOCKUS
ELECTRICAL-Final 4/15/2024 Not Ready for Inspection LILIANA PORTILLO
Final 4/15/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 4/15/2024 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 4/15/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 4/15/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/15/2024 SGSOV No Gas LILIANA PORTILLO
Service/Power Release 4/15/2024 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 4/15/2024 Not Ready for Inspection LILIANA PORTILLO
Final 5/21/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 6/28/2024 Approved SCOTT FINNILA
Final 6/28/2024 OK to Issue CofO SCOTT FINNILA
Green Building Final 6/28/2024 Approved SCOTT FINNILA
HVAC-Final 6/28/2024 Approved SCOTT FINNILA
PLUMBING-Final 6/28/2024 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Not Required SCOTT FINNILA
Service/Power Release 6/28/2024 Approved SCOTT FINNILA
Smoke Detectors 6/28/2024 Approved SCOTT FINNILA