1042 N EL PASO DR 90042
Certificate Information: 1042 N EL PASO DR 90042
- Application / Permit
- 22010-20000-01655
- Plan Check / Job No.
- B22VN04980
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT ( 48'-0"X26'-0" ) PER LAMC 12.22 A.33(c) and (d) FIRE SPRINKLER NFPA 13R
- Permit Issued
- Issued on 5/15/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/6/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 5/6/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/10/2022 | APPLICANT |
| Applicant returned to address corrections | 4/14/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/3/2023 | MOHAMMAD ESMAILI |
| Issued | 5/15/2023 | APPLICANT |
| CofO in Progress | 7/1/2024 | SCOTT FINNILA |
| CofO Issued | 7/3/2024 | DEROLD HAUFF |
| Permit Finaled | 7/3/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/5/2022 | MOHAMMAD ESMAILI |
| Address approval | Cleared | 5/27/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2022 | CINDY QI |
| Sewer availability | Cleared | 5/31/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 6/29/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 8/17/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 8/22/2022 | CINDY QI |
| GPI Written Notices | Cleared | 5/3/2023 | MOHAMMAD ESMAILI |
| Grading Preinspection | Not Cleared | 9/5/2023 | Department of Building and Safety |
| Grading Preinspection | Not Cleared | 6/28/2024 | Department of Building and Safety |
| Grading Preinspection | Not Cleared | 6/28/2024 | Department of Building and Safety |
| Grading Preinspection | Not Cleared | 6/28/2024 | Department of Building and Safety |
| Grading Preinspection | Not Cleared | 6/28/2024 | Department of Building and Safety |
| Grading Preinspection | Not Cleared | 6/28/2024 | Department of Building and Safety |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/12/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/12/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/16/2023 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/22/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/10/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 7/10/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 7/10/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 7/19/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 7/19/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/7/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 8/7/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 8/7/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 9/7/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/7/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/18/2023 | Conditional Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/18/2023 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 10/6/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/6/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 10/6/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/18/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/18/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/18/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/7/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/7/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/27/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/27/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/27/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/13/2023 | Approved | RICHARD DOCKUS |
| Insulation | 12/13/2023 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 4/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 4/15/2024 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 4/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 4/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 4/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV No Gas | LILIANA PORTILLO |
| Service/Power Release | 4/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 4/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 5/21/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 6/28/2024 | Approved | SCOTT FINNILA |
| Final | 6/28/2024 | OK to Issue CofO | SCOTT FINNILA |
| Green Building Final | 6/28/2024 | Approved | SCOTT FINNILA |
| HVAC-Final | 6/28/2024 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 6/28/2024 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/28/2024 | SGSOV Not Required | SCOTT FINNILA |
| Service/Power Release | 6/28/2024 | Approved | SCOTT FINNILA |
| Smoke Detectors | 6/28/2024 | Approved | SCOTT FINNILA |