5170 N AMESTOY AVE 91316
Certificate Information: 5170 N AMESTOY AVE 91316
- Application / Permit
- 22010-20000-01636
- Plan Check / Job No.
- B22VN04918
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW DETACHED COVERED PATIO
- Permit Issued
- Issued on 7/29/2022
- Issuing Office
- Current Status
- CofO Issued on 9/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | SELLA BENYAMIN |
| Corrections Issued | 4/19/2022 | SELLA BENYAMIN |
| Quality Review Completed | 4/26/2022 | STEVEN KIM |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Plan Check Approved | 7/29/2022 | SELLA BENYAMIN |
| Issued | 7/29/2022 | APPLICANT |
| CofO in Progress | 7/30/2025 | JON MCHUGH |
| CofO in Progress | 9/16/2025 | JON MCHUGH |
| Permit Finaled | 9/17/2025 | JOHN JANSON |
| CofO Issued | 9/17/2025 | JOHN JANSON |
| Permit Finaled | 9/17/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2022 | CARLOS AGUILERA |
| Permit | Cleared | 4/28/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/28/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 5/31/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/1/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/14/2022 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Steel/Welding | 9/28/2023 | No Access for Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 4/24/2024 | Partial Approval | JON MCHUGH |
| Deputy Reinf. Concrete | 4/25/2024 | Conditional Approval | JON MCHUGH |
| Deputy Other (see comments) | 4/26/2024 | Approved | JON MCHUGH |
| Deputy Drilled-In Anchors | 5/2/2024 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 5/2/2024 | Conditional Approval | JON MCHUGH |
| Underground Mechanical | 5/2/2024 | Partial Approval | JON MCHUGH |
| Deputy Reinf. Concrete | 5/3/2024 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2024 | Partial Approval | JON MCHUGH |
| Deputy Wood Construction | 5/20/2024 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 5/28/2024 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 5/28/2024 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 7/29/2024 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/5/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 6/5/2025 | Approved | JON MCHUGH |
| Final | 6/5/2025 | Not Ready for Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 6/5/2025 | Approved | JON MCHUGH |
| HVAC-Final | 6/5/2025 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/5/2025 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 6/5/2025 | Not Required | JON MCHUGH |
| Smoke Detectors | 6/5/2025 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 6/5/2025 | Approved | JON MCHUGH |
| Final | 7/30/2025 | OK to Issue CofO | JON MCHUGH |
| Special/Order Compliance | 8/7/2025 | Corrections Issued | JON MCHUGH |
| Pre-Inspection | 8/14/2025 | Partial Inspection | JON MCHUGH |
| Pre-Inspection | 8/19/2025 | Partial Inspection | JON MCHUGH |
| Special/Order Compliance | 8/19/2025 | Partial Inspection | SEAN WIRCH |
| Final | 9/15/2025 | OK to Issue CofO | JON MCHUGH |