5170 N AMESTOY AVE 91316
Certificate Information: 5170 N AMESTOY AVE 91316
- Application / Permit
- 22010-20000-01635
- Plan Check / Job No.
- B22VN04918
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 87'-6" X 38'-4" TWO STORY SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 7/29/2022
- Issuing Office
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | SELLA BENYAMIN |
| Corrections Issued | 4/19/2022 | SELLA BENYAMIN |
| Quality Review Completed | 4/26/2022 | STEVEN KIM |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Plan Check Approved | 7/29/2022 | SELLA BENYAMIN |
| Issued | 7/29/2022 | APPLICANT |
| CofO in Progress | 7/17/2025 | JON MCHUGH |
| CofO Issued | 7/31/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/31/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2022 | CARLOS AGUILERA |
| Permit | Cleared | 4/28/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/28/2022 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 5/13/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 5/20/2022 | MICHAEL GILLISSIE |
| Low Impact Development | Cleared | 5/31/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/1/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/30/2022 | Approved | SEAN HAUPT |
| Piling/Pier/Caisson | 9/9/2022 | Partial Approval | SEAN HAUPT |
| Deputy Wood Construction | 9/12/2022 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 9/30/2022 | Conditional Approval | MORRIS JACKSON |
| Deputy Steel/Welding | 10/3/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 10/6/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 10/17/2022 | Partial Approval | DAVID SCANTLIN |
| Deputy Reinf. Concrete | 10/18/2022 | Approved | SEAN HAUPT |
| Deputy Reinf. Concrete | 10/19/2022 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 11/14/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 11/14/2022 | Partial Approval | SEAN HAUPT |
| Deputy Other (see comments) | 11/15/2022 | Approved | SEAN HAUPT |
| Deputy Shotcrete | 11/16/2022 | Conditional Approval | MORRIS JACKSON |
| Deputy Shotcrete | 11/17/2022 | Conditional Approval | MORRIS JACKSON |
| Underground Mechanical | 11/29/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 12/27/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 1/12/2023 | Approved | JON MCHUGH |
| Special/Order Compliance | 1/12/2023 | Partial Inspection | SEAN WIRCH |
| Deputy Reinf. Concrete | 1/13/2023 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 4/12/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2023 | Partial Approval | DAVID SCANTLIN |
| Special/Order Compliance | 5/2/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/4/2023 | Partial Approval | JON MCHUGH |
| Deputy Steel/Welding | 5/12/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Partial Approval | JON MCHUGH |
| Deputy Wood Construction | 6/13/2023 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Partial Approval | JOHN KIDWELL |
| Deputy Steel/Welding | 6/21/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 8/25/2023 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Approval | JON MCHUGH |
| Sewer | 11/6/2023 | Partial Approval | JON MCHUGH |
| Underground Mechanical | 11/6/2023 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2023 | Partial Approval | JON MCHUGH |
| Shower Pan | 11/22/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 2/26/2024 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 2/27/2024 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 3/4/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 3/4/2024 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 3/27/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 3/27/2024 | Approved | ALEXANDER HANDY |
| Green Building Rough | 3/27/2024 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 3/27/2024 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 4/5/2024 | Approved | JON MCHUGH |
| Insulation | 4/5/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 4/9/2024 | Approved | JON MCHUGH |
| Insulation | 4/9/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 4/29/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/29/2024 | Approved | GEVORK IPCHYAN |
| Gas Test | 10/24/2024 | Approved | JON MCHUGH |
| Underground Mechanical | 10/24/2024 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Final | 5/14/2025 | Corrections Issued | JON MCHUGH |
| HVAC-Final | 5/14/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 5/14/2025 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 5/14/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 5/27/2025 | Approved | JON MCHUGH |
| HVAC-Final | 5/27/2025 | Approved | JON MCHUGH |
| Final | 6/5/2025 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 6/5/2025 | Approved | JON MCHUGH |
| Green Building Final | 6/5/2025 | Approved | JON MCHUGH |
| Smoke Detectors | 6/5/2025 | Approved | JON MCHUGH |
| Final | 7/16/2025 | OK to Issue CofO | JON MCHUGH |