907 W 30TH ST 90007
Certificate Information: 907 W 30TH ST 90007
- Application / Permit
- 22010-20000-01620
- Plan Check / Job No.
- B22VN04856
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW CONSTRUCTION ADU. the LID clearance has been deferred. approval for LID requirements shall be obtained from LASAN prior to the issuance of CofO
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Current Status
- CofO Issued on 6/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 4/18/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/19/2022 | HERNAN ARREOLA |
| Plan Check Approved | 11/18/2022 | ARSALAN SHABESTARI |
| Issued | 11/18/2022 | APPLICANT |
| CofO in Progress | 6/14/2024 | BRENDAN MORELLI |
| CofO in Progress | 6/14/2024 | SCOTT FINNILA |
| CofO in Progress | 6/26/2024 | BRENDAN MORELLI |
| CofO Issued | 6/27/2024 | DEROLD HAUFF |
| Permit Finaled | 6/27/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 4/19/2022 | MAX LODER |
| ZA Case | Cleared | 4/19/2022 | JASON CHAN |
| ZI | Cleared | 4/19/2022 | JASON CHAN |
| Address approval | Cleared | 4/22/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2022 | JEANIE LAM |
| Sewer availability | Cleared | 4/22/2022 | JEANIE LAM |
| Redevelopment Project Area | Cleared | 5/2/2022 | SUSAN WONG |
| Roof/Waste drainage to street | Cleared | 7/27/2022 | JEANIE LAM |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: NA35389 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 5/17/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 5/17/2023 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Approved | BRENDAN MORELLI |
| METHANE-Barrier | 5/23/2023 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 7/11/2023 | Conditional Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 7/11/2023 | Conditional Approval | BRENDAN MORELLI |
| Sewer | 7/11/2023 | Approved | BRENDAN MORELLI |
| Deputy Wood Construction | 7/13/2023 | Conditional Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 7/21/2023 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 7/21/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| METHANE-Rough | 7/21/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 7/21/2023 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 7/21/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/10/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 8/10/2023 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 8/10/2023 | Conditional Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 8/10/2023 | Partial Approval | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 8/10/2023 | Approved | BRENDAN MORELLI |
| Insulation | 8/16/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/21/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/21/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/13/2024 | OK to Issue CofO | BRENDAN MORELLI |
| Footing/Foundation/Slab | 6/13/2024 | Approved | BRENDAN MORELLI |
| Gas Test | 6/13/2024 | Approved | BRENDAN MORELLI |
| Green Building Final | 6/13/2024 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 6/13/2024 | SGSOV Approved | BRENDAN MORELLI |
| Service/Power Release | 6/13/2024 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 6/13/2024 | Approved | BRENDAN MORELLI |