4953-4955 N HASKELL AVE 91436

Certificate Information: 4953-4955 N HASKELL AVE 91436

Application / Permit
22010-20000-01600
Plan Check / Job No.
B22VN04813
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRR. SHAPED 60'-11" x 87'-2" TWO-STORY SINGLE FAMILY DWELLING WITH ATT. TWO-CAR GARAGE AND ATT. ONE-STORY ACCESSORY DWELLING UNIT (PER LAMC 12.22 A.33(c) and (e)) AND OPEN TRELLIS; AUTOMATIC SPRINKLER SYSTEM IS REQ'D
Permit Issued
Issued on 8/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 SEAN SHAHMIRI
Corrections Issued 4/28/2022 SEAN SHAHMIRI
Quality Review Completed 5/2/2022 OMID HEDAYAT
Building Plans Picked Up 5/12/2022 APPLICANT
Plan Check Approved 8/22/2022 SEAN SHAHMIRI
Issued 8/29/2022 APPLICANT
CofO in Progress 7/14/2023 VINCENT HANLEY
CofO Issued 12/7/2023 JOHN JANSON
Permit Finaled 12/7/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/2/2022 CARLOS AGUILERA
Permit Cleared 5/2/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/3/2022 CARLOS AGUILERA
Sewer availability Cleared 5/3/2022 CARLOS AGUILERA
Trees in Parkway Cleared 5/24/2022 ADALBERTO VERA
Construction within easement Cleared 6/3/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 7/10/2022 JOHN CONNEALLY
Low Impact Development Cleared 8/3/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 8/5/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/11/2022 Partial Approval VINCENT HANLEY
Sewer 10/11/2022 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 11/1/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 11/1/2022 Approved VINCENT HANLEY
Deputy Reinf. Concrete 11/2/2022 Approved VINCENT HANLEY
Sewer 11/10/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 12/2/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/15/2022 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Not Ready for Inspection VINCENT HANLEY
Gas Test 12/15/2022 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 12/15/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/22/2022 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Approved VINCENT HANLEY
Gas Test 12/22/2022 Approved VINCENT HANLEY
Deputy Wood Construction 12/23/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/29/2022 Approved VINCENT HANLEY
Green Building Rough 12/29/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 12/29/2022 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 1/4/2023 Approved VINCENT HANLEY
Special/Order Compliance 1/4/2023 Partial Inspection JESUS PINEDA
Verify Sprinkler Sign Off 1/4/2023 Approved VINCENT HANLEY
Wood Frame 1/4/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/10/2023 Partial Approval VINCENT HANLEY
Shower Pan 1/10/2023 Approved VINCENT HANLEY
Insulation 1/24/2023 Conditional Approval JESUS PINEDA
Interior/Exterior Lathing 1/26/2023 Approved VINCENT HANLEY
Drywall Nailing 1/31/2023 Approved VINCENT HANLEY
Special/Order Compliance 5/24/2023 Approved VINCENT HANLEY
HVAC-Final 5/25/2023 Approved VINCENT HANLEY
PLUMBING-Final 6/23/2023 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Final 6/30/2023 Approved VINCENT HANLEY
PLUMBING-Final 6/30/2023 Approved VINCENT HANLEY
Final 7/13/2023 OK to Issue CofO VINCENT HANLEY
Green Building Final 7/13/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Approved VINCENT HANLEY
Service/Power Release 7/13/2023 Approved VINCENT HANLEY
Smoke Detectors 7/13/2023 Approved VINCENT HANLEY