7527 N CLYBOURN AVE 91352

Certificate Information: 7527 N CLYBOURN AVE 91352

Application / Permit
22010-20000-01598
Plan Check / Job No.
B22VN04800
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY 1200 SF ADU AND STORAGE 235 SF PER LAMC 12.22 A.33 (c) and (d). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 8/31/2022
Issuing Office
Current Status
CofO Issued on 8/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 ALEC MOUSAKHANIAN
Corrections Issued 4/28/2022 ALEC MOUSAKHANIAN
Corrections Issued 5/11/2022 ALEC MOUSAKHANIAN
Quality Review Completed 5/12/2022 STEVEN KIM
Building Plans Picked Up 5/16/2022 APPLICANT
Applicant returned to address corrections 8/3/2022 ALEC MOUSAKHANIAN
Plan Check Approved 8/31/2022 ALEC MOUSAKHANIAN
Issued 8/31/2022 APPLICANT
CofO in Progress 3/16/2023 JOHN HAYES
Permit Finaled 8/25/2023 RUBEN SALAS
CofO Issued 8/25/2023 RUBEN SALAS
Permit Finaled 8/25/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/19/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/27/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 7/27/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 8/4/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/8/2022 Approved JOHN HAYES
Footing/Foundation/Slab 9/13/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/22/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/24/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 No Access for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 10/7/2022 Partial Approval JOHN HAYES
Deputy Wood Construction 10/12/2022 Conditional Approval JOHN HAYES
ELECTRICAL-Rough 10/14/2022 Approved JOHN HAYES
PLUMBING-Rough 10/14/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 10/21/2022 Approved JOHN HAYES
Green Building Rough 10/21/2022 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 10/21/2022 Approved JOHN HAYES
Verify Sprinkler Sign Off 10/21/2022 Approved JOHN HAYES
Insulation 10/28/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 10/28/2022 Approved CALEB MEISTER
Shower Pan 10/28/2022 Approved CALEB MEISTER
Drywall Nailing 11/3/2022 Approved JOHN HAYES
ELECTRICAL-Final 11/3/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 2/28/2023 Not Ready for Inspection JOHN HAYES
Final 2/28/2023 Corrections Issued JOHN HAYES
Green Building Final 2/28/2023 Approved JOHN HAYES
HVAC-Final 2/28/2023 Approved JOHN HAYES
PLUMBING-Final 2/28/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Not Ready JOHN HAYES
Service/Power Release 2/28/2023 Not Ready for Inspection JOHN HAYES
Smoke Detectors 2/28/2023 Approved JOHN HAYES
Final 3/8/2023 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved JOHN HAYES
Service/Power Release 3/8/2023 Not Ready for Inspection JOHN HAYES
Final 3/15/2023 OK to Issue CofO JOHN HAYES
Service/Power Release 3/15/2023 Approved JOHN HAYES