7709 N LOUISE AVE 91325

Certificate Information: 7709 N LOUISE AVE 91325

Application / Permit
22010-20000-01592
Plan Check / Job No.
B22VN04749
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1200 SQ. FT. DETACHED 2-STORY ADU PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 8/25/2022
Issuing Office
Current Status
CofO Issued on 12/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 ALEC MOUSAKHANIAN
Corrections Issued 4/27/2022 ALEC MOUSAKHANIAN
Quality Review Completed 5/10/2022 STEVEN KIM
Building Plans Picked Up 5/16/2022 APPLICANT
Plan Check Approved 8/25/2022 ALEC MOUSAKHANIAN
Issued 8/25/2022 APPLICANT
CofO in Progress 11/26/2024 GAREN HAYRAPETYAN
Permit Finaled 12/12/2024 RUBEN SALAS
CofO Issued 12/12/2024 RUBEN SALAS
Permit Finaled 12/12/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/17/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 5/18/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 5/18/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 8/9/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 8/9/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 8/9/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 8/9/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/9/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 8/9/2023 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 8/23/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 8/23/2023 Not Ready for Inspection RAUL OLAGI
Sewer 8/23/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 8/24/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 10/10/2023 Corrections Issued RAUL OLAGI
Sewer 10/10/2023 Approved RAUL OLAGI
Underground Mechanical 10/10/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 10/16/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 No Access for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/28/2023 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 2/6/2024 Not Ready for Inspection RAUL OLAGI
Green Building Rough 2/6/2024 Not Ready for Inspection RAUL OLAGI
Rough-Elec/Plmb/HVAC 2/6/2024 Not Ready for Inspection RAUL OLAGI
Verify Sprinkler Sign Off 2/6/2024 Approved RAUL OLAGI
ELECTRICAL-Rough 2/8/2024 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/8/2024 Approved RAUL OLAGI
HVAC-Rough 2/8/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 2/8/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 2/20/2024 Partial Approval RAUL OLAGI
Interior/Exterior Lathing 2/20/2024 Partial Approval RAUL OLAGI
Rough-Elec/Plmb/HVAC 2/20/2024 Approved RAUL OLAGI
Shower Pan 2/20/2024 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 2/29/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/29/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 2/29/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 2/29/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 3/4/2024 No Access for Inspection SALVADOR MARTINEZ
Drywall Nailing 3/6/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 8/19/2024 Corrections Issued RAUL OLAGI
Final 8/19/2024 Corrections Issued RAUL OLAGI
HVAC-Final 8/19/2024 Corrections Issued RAUL OLAGI
PLUMBING-Final 8/19/2024 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 8/19/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 8/19/2024 Approved RAUL OLAGI
ELECTRICAL-Final 9/12/2024 Approved RAUL OLAGI
HVAC-Final 9/12/2024 Approved RAUL OLAGI
PLUMBING-Final 9/12/2024 Approved RAUL OLAGI
Final 11/26/2024 OK to Issue CofO GAREN HAYRAPETYAN
Green Building Final 11/26/2024 Approved GAREN HAYRAPETYAN
Service/Power Release 11/26/2024 Approved GAREN HAYRAPETYAN