5056 N LOUISE AVE 91316

Certificate Information: 5056 N LOUISE AVE 91316

Application / Permit
22010-20000-01579
Plan Check / Job No.
B22VN04720
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRR SHAPED 99'-3" x 57'-2 1/2" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND ATT. OPEN TRELLIS; NFPA 13D THRU-OUT
Permit Issued
Issued on 12/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 SEAN SHAHMIRI
Corrections Issued 4/18/2022 SEAN SHAHMIRI
Quality Review Completed 4/22/2022 OMID HEDAYAT
Building Plans Picked Up 4/25/2022 APPLICANT
Applicant returned to address corrections 8/2/2022 SEAN SHAHMIRI
Applicant returned to address corrections 12/14/2022 SEAN SHAHMIRI
Applicant returned to address corrections 12/23/2022 SEAN SHAHMIRI
Plan Check Approved 12/23/2022 SEAN SHAHMIRI
Issued 12/23/2022 APPLICANT
CofO in Progress 8/4/2025 JON MCHUGH
CofO in Progress 9/8/2025 SEAN WIRCH
Permit Finaled 9/11/2025 JOHN JANSON
CofO Issued 9/11/2025 JOHN JANSON
Permit Finaled 9/11/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/11/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/12/2022 MEGAN GODINEZ
Permit Cleared 5/12/2022 MEGAN GODINEZ
Sewer availability Cleared 5/12/2022 MEGAN GODINEZ
Trees in Parkway Cleared 6/6/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 8/29/2022 GILBERT URREA
Low Impact Development Cleared 11/21/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 11/22/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Freitas,, Richard Gomes; Lic. No.: C49072 240 COPA DE ORO DR      BREA, CA 92823

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/9/2023 Not Ready for Inspection JON MCHUGH
Footing/Foundation/Slab 4/6/2023 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 4/25/2023 Corrections Issued JON MCHUGH
PLUMBING-Rough 4/25/2023 Partial Approval JON MCHUGH
Footing/Foundation/Slab 4/28/2023 Partial Approval JON MCHUGH
Footing/Foundation/Slab 5/18/2023 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 7/18/2023 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/29/2023 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 8/31/2023 Not Ready for Inspection JON MCHUGH
Green Building Rough 8/31/2023 Not Ready for Inspection JON MCHUGH
Verify Sprinkler Sign Off 8/31/2023 Not Ready for Inspection JON MCHUGH
Wood Frame 8/31/2023 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Partial Approval JON MCHUGH
Gas Test 11/2/2023 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 11/2/2023 Corrections Issued JON MCHUGH
Sewer 11/2/2023 Not Ready for Inspection JON MCHUGH
Sewer 11/6/2023 Partial Approval JOHN KIDWELL
Sewer 11/13/2023 Approved JEFFREY PARD
PLUMBING-Rough 12/29/2023 Approved JON MCHUGH
HVAC-Final 1/8/2024 Corrections Issued JON MCHUGH
HVAC-Rough 1/8/2024 Corrections Issued JON MCHUGH
Shower Pan 1/8/2024 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 1/31/2024 Approved JON MCHUGH
Interior/Exterior Lathing 1/31/2024 Partial Approval JON MCHUGH
BUILDING-Rough-Frame 2/26/2024 Not Ready for Inspection JON MCHUGH
Green Building Rough 2/26/2024 Not Ready for Inspection JON MCHUGH
Verify Sprinkler Sign Off 2/26/2024 Not Ready for Inspection JON MCHUGH
Wood Frame 2/26/2024 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 3/11/2024 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Not Ready for Inspection JON MCHUGH
Green Building Rough 3/11/2024 Approved JON MCHUGH
Verify Sprinkler Sign Off 3/11/2024 Not Ready for Inspection JON MCHUGH
Shower Pan 3/12/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 3/19/2024 Partial Approval JON MCHUGH
Verify Sprinkler Sign Off 3/19/2024 Approved JON MCHUGH
Insulation 4/1/2024 Approved JON MCHUGH
Drywall Nailing 4/10/2024 Not Ready for Inspection JON MCHUGH
Drywall Nailing 4/17/2024 Approved JON MCHUGH
Shower Pan 4/30/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 8/6/2024 SGSOV Not Ready MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 8/15/2024 SGSOV Not Ready MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 8/21/2024 SGSOV Not Ready MORRIS JACKSON
ELECTRICAL-Final 8/27/2024 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 8/27/2024 SGSOV Approved JON MCHUGH
ELECTRICAL-Final 9/3/2024 Corrections Issued JON MCHUGH
Green Building Final 9/3/2024 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 10/10/2024 Corrections Issued JON MCHUGH
ELECTRICAL-Final 10/15/2024 Corrections Issued JON MCHUGH
Service/Power Release 10/15/2024 Approved JON MCHUGH
ELECTRICAL-Final 11/6/2024 Not Ready for Inspection JON MCHUGH
Green Building Final 11/6/2024 Not Ready for Inspection JON MCHUGH
PLUMBING-Final 11/6/2024 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 4/10/2025 Approved JON MCHUGH
ELECTRICAL-Final 4/10/2025 Not Ready for Inspection JON MCHUGH
Final 4/10/2025 Corrections Issued JON MCHUGH
Green Building Final 4/10/2025 Not Ready for Inspection JON MCHUGH
PLUMBING-Final 4/10/2025 Not Ready for Inspection JON MCHUGH
Smoke Detectors 4/10/2025 Not Ready for Inspection JON MCHUGH
Final 7/24/2025 Corrections Issued JON MCHUGH
Green Building Final 7/24/2025 Approved JON MCHUGH
Smoke Detectors 7/24/2025 Approved JON MCHUGH
ELECTRICAL-Final 7/30/2025 Approved JON MCHUGH
Final 7/30/2025 Corrections Issued JON MCHUGH
HVAC-Final 7/30/2025 No Access for Inspection JON MCHUGH
PLUMBING-Final 7/30/2025 Approved JON MCHUGH
Final 8/4/2025 OK to Issue CofO JON MCHUGH