5220 N WHITSETT AVE 91607

Certificate Information: 5220 N WHITSETT AVE 91607

Application / Permit
22010-20000-01546
Plan Check / Job No.
B22VN04655
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ADU W/ ATTACHED 2-CAR GARAGE PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 8/11/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2022 APPLICANT
Assigned to Plan Check Engineer 4/7/2022 MAHNAZ NOURHASHEMI
Corrections Issued 4/14/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 4/22/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 4/26/2022 APPLICANT
Applicant returned to address corrections 8/3/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 8/5/2022 MAHNAZ NOURHASHEMI
Issued 8/11/2022 APPLICANT
Refund in Progress 8/30/2022 SELENIA GARCIA
Refund Closed 8/30/2022 SELENIA GARCIA
Issued 8/30/2022 SELENIA GARCIA
CofO in Progress 2/27/2023 ARAM AVEDISIAN
CofO Issued 3/13/2023 DANIEL ORRANTE
Permit Finaled 3/13/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/25/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/25/2022 CARLOS AGUILERA
Highway dedication Cleared 4/25/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 5/16/2022 LAURINDA MEADE
Low Impact Development Cleared 6/24/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/27/2022 CARLOS AGUILERA
Sewer availability Cleared 6/27/2022 CARLOS AGUILERA
Specific Plan Cleared 7/5/2022 CORREY KITCHENS
ZI Cleared 7/22/2022 ANDREW JORGENSEN

Contact Information

Architect Stockton,, Richard Kenneth; Lic. No.: C35492 20140 ZIMMERMAN PLACE      SANTA CLARITA, CA 91390
Contractor Owner-Builder       ,
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/30/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Rough 9/30/2022 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 10/7/2022 Approved RAFAEL CORTES
Pre-Inspection 10/14/2022 Not Ready for Inspection DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 10/21/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 10/21/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 11/2/2022 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/10/2022 Approved CALEB MEISTER
Gas Test 11/10/2022 Approved CALEB MEISTER
PLUMBING-Rough 11/10/2022 Corrections Issued CALEB MEISTER
HVAC-Rough 11/17/2022 Approved CALEB MEISTER
PLUMBING-Rough 11/17/2022 Approved CALEB MEISTER
Shower Pan 11/17/2022 Not Ready for Inspection CALEB MEISTER
Insulation 11/29/2022 Approved KIRK SANDERS
Drywall Nailing 12/6/2022 Corrections Issued KIRK SANDERS
Green Building Rough 12/6/2022 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 12/6/2022 Approved KIRK SANDERS
BUILDING-Rough-Frame 12/16/2022 Partial Approval KIRK SANDERS
Green Building Rough 12/16/2022 Partial Approval KIRK SANDERS
Verify Sprinkler Sign Off 12/16/2022 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 1/20/2023 Partial Approval ROBERT GOLD
Drywall Nailing 1/20/2023 Not Ready for Inspection ROBERT GOLD
Final 1/20/2023 Corrections Issued ROBERT GOLD
Green Building Final 1/20/2023 Not Ready for Inspection ROBERT GOLD
Green Building Rough 1/20/2023 Not Ready for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Not Ready ROBERT GOLD
Service/Power Release 1/20/2023 Not Ready for Inspection ROBERT GOLD
Smoke Detectors 1/20/2023 Not Ready for Inspection ROBERT GOLD
Verify Sprinkler Sign Off 1/20/2023 Not Ready for Inspection ROBERT GOLD
BUILDING-Rough-Frame 2/6/2023 Approved KIRK SANDERS
Drywall Nailing 2/6/2023 Approved KIRK SANDERS
Final 2/6/2023 No Access for Inspection KIRK SANDERS
Green Building Final 2/6/2023 No Access for Inspection KIRK SANDERS
Green Building Rough 2/6/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Not Ready KIRK SANDERS
Service/Power Release 2/6/2023 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 2/6/2023 No Access for Inspection KIRK SANDERS
Final 2/21/2023 Corrections Issued KIRK SANDERS
Green Building Final 2/21/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 2/21/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 2/21/2023 Corrections Issued KIRK SANDERS
Smoke Detectors 2/21/2023 Approved KIRK SANDERS
ELECTRICAL-Final 2/27/2023 Approved ARAM AVEDISIAN
Final 2/27/2023 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 2/27/2023 Approved ARAM AVEDISIAN