8137 N JUMILLA AVE 91306
Certificate Information: 8137 N JUMILLA AVE 91306
- Application / Permit
- 22010-20000-01515
- Plan Check / Job No.
- B22VN04557
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28'-2" X 30' 1-STORY IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2022 | RAPHAEL ROSAS |
| Corrections Issued | 4/11/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 4/14/2022 | STEVEN KIM |
| Building Plans Picked Up | 4/18/2022 | APPLICANT |
| Plan Check Approved | 8/8/2022 | RAPHAEL ROSAS |
| Issued | 9/2/2022 | APPLICANT |
| CofO in Progress | 11/23/2022 | STEVEN BACK |
| Permit Finaled | 11/28/2022 | JOHN JANSON |
| CofO Issued | 11/28/2022 | JOHN JANSON |
| Permit Finaled | 11/28/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/27/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 6/22/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/28/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/8/2022 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 9/13/2022 | Approved | STEVEN BACK |
| Sewer | 9/13/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Final | 9/26/2022 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Approved | PETER FOLLING |
| Green Building Rough | 9/26/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Final | 9/26/2022 | Approved | PETER FOLLING |
| PLUMBING-Final | 9/26/2022 | Corrections Issued | PETER FOLLING |
| Verify Sprinkler Sign Off | 9/26/2022 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 9/30/2022 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 9/30/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 9/30/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 9/30/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/4/2022 | Approved | DAVID SANDOVAL |
| Insulation | 10/4/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 10/6/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/12/2022 | Approved | STEVEN BACK |
| Final | 11/10/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 11/10/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | STEVEN BACK |
| Service/Power Release | 11/10/2022 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 11/10/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 11/23/2022 | Approved | STEVEN BACK |
| Final | 11/23/2022 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Approved | STEVEN BACK |