13845 N LEXICON AVE 91342
Certificate Information: 13845 N LEXICON AVE 91342
- Application / Permit
- 22010-20000-01480
- Plan Check / Job No.
- B22VN04422
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New 1-story metal stud framing accessory dwelling unit (ADU) per CA Govt. Code 65852.2(e)
- Permit Issued
- Issued on 10/4/2022
- Issuing Office
- Current Status
- CofO Issued on 3/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | TU HUA |
| Corrections Issued | 5/6/2022 | TU HUA |
| Building Plans Picked Up | 5/18/2022 | APPLICANT |
| Quality Review Completed | 5/19/2022 | CHAD DOI |
| Plan Check Approved | 9/23/2022 | TU HUA |
| Issued | 10/4/2022 | APPLICANT |
| CofO in Progress | 12/4/2023 | KEVIN BERBERYAN |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
| CofO Issued | 3/2/2024 | RUBEN SALAS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/9/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 5/11/2022 | ROSE MARIE SMITH |
| Low Impact Development | Cleared | 6/21/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 6/23/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 7/14/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/14/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Adu Concepts; Lic. No.: 1018294-B | , |
| Contractor | Green Source Energy Inc; Lic. No.: 1018294-B | , |
| Engineer | Yiu,, Siu Fung; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/21/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 11/28/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/28/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 11/28/2022 | Approved | MICHEL ABAJAN |
| Deputy Reinf. Concrete | 11/29/2022 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 11/30/2022 | No Result Entered | KENNETH KUROWSKI |
| Pre-Inspection | 12/7/2022 | Partial Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/29/2022 | Partial Approval | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 12/29/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/13/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 1/13/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/13/2023 | Partial Inspection | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 1/13/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 1/17/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 1/17/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 2/23/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/7/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 4/7/2023 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 4/7/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 4/7/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2023 | SGSOV Not Ready | ARAM AVEDISIAN |
| Service/Power Release | 4/7/2023 | Not Required | ARAM AVEDISIAN |
| Smoke Detectors | 4/7/2023 | Approved | ARAM AVEDISIAN |
| Final | 10/3/2023 | Corrections Issued | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 10/3/2023 | SGSOV Not Ready | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Not Ready | KEVIN BERBERYAN |
| Final | 11/29/2023 | Corrections Issued | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Approved | KEVIN BERBERYAN |
| Final | 12/1/2023 | OK to Issue CofO | KEVIN BERBERYAN |