12965 N HERRICK AVE 91342

Certificate Information: 12965 N HERRICK AVE 91342

Application / Permit
22010-20000-01477
Plan Check / Job No.
B22VN04416
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 8/26/2022
Issuing Office
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 DANIEL YIP
Corrections Issued 5/13/2022 CARLOS MONTES
Applicant returned to address corrections 7/28/2022 DANIEL YIP
Applicant returned to address corrections 8/6/2022 DANIEL YIP
Applicant returned to address corrections 8/15/2022 DANIEL YIP
Applicant returned to address corrections 8/19/2022 DANIEL YIP
Plan Check Approved 8/26/2022 DANIEL YIP
Issued 8/26/2022 APPLICANT
CofO in Progress 7/29/2024 KEVIN BERBERYAN
Permit Finaled 8/5/2024 RUBEN SALAS
CofO Issued 8/5/2024 RUBEN SALAS
Permit Finaled 8/5/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/1/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/2/2022 CARLOS AGUILERA
Sewer availability Cleared 6/2/2022 CARLOS AGUILERA
Low Impact Development Cleared 8/2/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 8/3/2022 CARLOS AGUILERA
Miscellaneous Cleared 8/26/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/14/2022 Partial Inspection ARAM AVEDISIAN
PLUMBING-Rough 10/4/2022 Partial Approval CALEB MEISTER
Footing/Foundation/Slab 10/7/2022 Conditional Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 10/11/2022 Approved ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 10/11/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/15/2022 Not Ready for Inspection ARAM AVEDISIAN
Green Building Rough 11/15/2022 Not Ready for Inspection ARAM AVEDISIAN
Verify Sprinkler Sign Off 11/15/2022 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 12/9/2022 Corrections Issued ARAM AVEDISIAN
Gas Test 12/9/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 12/9/2022 Approved ARAM AVEDISIAN
Sewer 12/9/2022 Approved ARAM AVEDISIAN
Underground Mechanical 12/9/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/14/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 12/14/2022 Approved ARAM AVEDISIAN
Green Building Rough 12/14/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/14/2022 Partial Approval ARAM AVEDISIAN
Verify Sprinkler Sign Off 12/14/2022 Approved ARAM AVEDISIAN
Insulation 12/20/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 12/21/2022 Approved ARAM AVEDISIAN
Drywall Nailing 12/29/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/29/2022 Partial Approval ARAM AVEDISIAN
Shower Pan 12/29/2022 Approved ARAM AVEDISIAN
Final 8/15/2023 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 8/15/2023 Approved KEVIN BERBERYAN
Green Building Final 8/15/2023 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Not Ready KEVIN BERBERYAN
Service/Power Release 8/15/2023 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 8/15/2023 Not Ready for Inspection KEVIN BERBERYAN
Final 9/25/2023 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/25/2023 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Not Ready KEVIN BERBERYAN
Service/Power Release 9/25/2023 Corrections Issued KEVIN BERBERYAN
Smoke Detectors 9/25/2023 Approved KEVIN BERBERYAN
Final 10/12/2023 Corrections Issued KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 10/12/2023 Not Ready for Inspection KEVIN BERBERYAN
Final 10/16/2023 Conditional Approval KEVIN BERBERYAN
Service/Power Release 10/16/2023 Not Ready for Inspection KEVIN BERBERYAN
Final 7/29/2024 OK to Issue CofO KEVIN BERBERYAN
Service/Power Release 7/29/2024 Approved KEVIN BERBERYAN