12965 N HERRICK AVE 91342
Certificate Information: 12965 N HERRICK AVE 91342
- Application / Permit
- 22010-20000-01477
- Plan Check / Job No.
- B22VN04416
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | DANIEL YIP |
| Corrections Issued | 5/13/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 7/28/2022 | DANIEL YIP |
| Applicant returned to address corrections | 8/6/2022 | DANIEL YIP |
| Applicant returned to address corrections | 8/15/2022 | DANIEL YIP |
| Applicant returned to address corrections | 8/19/2022 | DANIEL YIP |
| Plan Check Approved | 8/26/2022 | DANIEL YIP |
| Issued | 8/26/2022 | APPLICANT |
| CofO in Progress | 7/29/2024 | KEVIN BERBERYAN |
| Permit Finaled | 8/5/2024 | RUBEN SALAS |
| CofO Issued | 8/5/2024 | RUBEN SALAS |
| Permit Finaled | 8/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/2/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 8/2/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/3/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 8/26/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/14/2022 | Partial Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/4/2022 | Partial Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 10/7/2022 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 10/11/2022 | Approved | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 11/15/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 11/15/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 11/15/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/9/2022 | Corrections Issued | ARAM AVEDISIAN |
| Gas Test | 12/9/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/9/2022 | Approved | ARAM AVEDISIAN |
| Sewer | 12/9/2022 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 12/9/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/14/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/14/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/14/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/14/2022 | Partial Approval | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 12/14/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 12/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 12/21/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 12/29/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/29/2022 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 12/29/2022 | Approved | ARAM AVEDISIAN |
| Final | 8/15/2023 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 8/15/2023 | Approved | KEVIN BERBERYAN |
| Green Building Final | 8/15/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 8/15/2023 | SGSOV Not Ready | KEVIN BERBERYAN |
| Service/Power Release | 8/15/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 8/15/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 9/25/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/25/2023 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/25/2023 | SGSOV Not Ready | KEVIN BERBERYAN |
| Service/Power Release | 9/25/2023 | Corrections Issued | KEVIN BERBERYAN |
| Smoke Detectors | 9/25/2023 | Approved | KEVIN BERBERYAN |
| Final | 10/12/2023 | Corrections Issued | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | KEVIN BERBERYAN |
| Service/Power Release | 10/12/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 10/16/2023 | Conditional Approval | KEVIN BERBERYAN |
| Service/Power Release | 10/16/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 7/29/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| Service/Power Release | 7/29/2024 | Approved | KEVIN BERBERYAN |