2944 S VIRGINIA ROAD 90016
Certificate Information: 2944 S VIRGINIA ROAD 90016
- Application / Permit
- 22010-20000-01476
- Plan Check / Job No.
- B22VN04415
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY 28' X 24' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 8/31/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | ROSENDO MEDINA |
| Corrections Issued | 3/27/2022 | ROSENDO MEDINA |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Applicant returned to address corrections | 8/15/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 8/26/2022 | GURUNATH NESARAJAH |
| Issued | 8/31/2022 | APPLICANT |
| CofO in Progress | 10/25/2023 | CALEB MEISTER |
| CofO Issued | 11/3/2023 | DEROLD HAUFF |
| Permit Finaled | 11/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/1/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2022 | CINDY QI |
| Sewer availability | Cleared | 4/5/2022 | CINDY QI |
| Construction near power lines | Cleared | 6/30/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 8/9/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/9/2022 | CINDY QI |
Contact Information
| Contractor | Cra Builders Group Inc; Lic. No.: 1088028-B | 6016 NOTRE DAME APT 422 CHINO, CA 91710 |
| Engineer | Grigoryan,, Souren Krist; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/13/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Barrier | 9/13/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Subgrade | 9/13/2022 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 9/13/2022 | Partial Approval | STUART CHAPMAN |
| Pre-Inspection | 9/13/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 9/20/2022 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 9/20/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Subgrade | 9/20/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/14/2022 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 10/14/2022 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 10/14/2022 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 11/28/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/28/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/6/2022 | Corrections Issued | STUART CHAPMAN |
| Deputy Wood Construction | 12/6/2022 | Conditional Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/6/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 12/6/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 12/15/2022 | Approved | MICHAEL LEWIS |
| Insulation | 12/21/2022 | Conditional Approval | CALEB MEISTER |
| Interior/Exterior Lathing | 12/21/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 12/29/2022 | Partial Inspection | CALEB MEISTER |
| Drywall Nailing | 12/29/2022 | Approved | CALEB MEISTER |
| Green Building Rough | 12/29/2022 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Not Ready | CALEB MEISTER |
| Pre-Inspection | 3/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/28/2023 | Approved | CALEB MEISTER |
| Final | 3/28/2023 | Corrections Issued | CALEB MEISTER |
| Footing/Foundation/Slab | 3/28/2023 | Approved | CALEB MEISTER |
| Green Building Final | 3/28/2023 | Corrections Issued | CALEB MEISTER |
| METHANE-Final | 3/28/2023 | Approved | CALEB MEISTER |
| METHANE-Rough | 3/28/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 3/28/2023 | SGSOV Approved | CALEB MEISTER |
| Service/Power Release | 3/28/2023 | Not Ready for Inspection | CALEB MEISTER |
| Smoke Detectors | 3/28/2023 | Approved | CALEB MEISTER |
| Verify Sprinkler Sign Off | 3/28/2023 | Approved | CALEB MEISTER |
| Final | 5/4/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 5/4/2023 | Not Ready for Inspection | CALEB MEISTER |
| Service/Power Release | 5/4/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 6/8/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 6/8/2023 | Approved | CALEB MEISTER |
| Service/Power Release | 6/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 9/8/2023 | No Access for Inspection | CALEB MEISTER |
| Service/Power Release | 9/8/2023 | No Access for Inspection | CALEB MEISTER |
| Final | 10/25/2023 | OK to Issue CofO | CALEB MEISTER |
| Service/Power Release | 10/25/2023 | Approved | CALEB MEISTER |