12819 W GILMORE AVE 90066

Certificate Information: 12819 W GILMORE AVE 90066

Application / Permit
22010-20000-01466
Plan Check / Job No.
B22VN04377
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 61'-11" X 27'-10" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/13/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 SELLA BENYAMIN
Corrections Issued 4/5/2022 SELLA BENYAMIN
Quality Review Completed 4/7/2022 STEVEN KIM
Building Plans Picked Up 4/13/2022 APPLICANT
Applicant returned to address corrections 6/28/2022 SELLA BENYAMIN
Plan Check Approved 9/1/2022 SELLA BENYAMIN
Issued 10/13/2022 APPLICANT
CofO in Progress 6/27/2023 HERBERT GIRON
Permit Finaled 6/30/2023 DANIEL ORRANTE
CofO Issued 6/30/2023 DANIEL ORRANTE
Permit Finaled 6/30/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/31/2022 SAUL GARCIA
Permit Cleared 5/31/2022 SAUL GARCIA
Sewer availability Cleared 5/31/2022 SAUL GARCIA
Hydrant and Access approval Cleared 6/10/2022 KURT CORRAL
Trees in Parkway Cleared 7/27/2022 ADALBERTO VERA
Low Impact Development Cleared 8/17/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 8/20/2022 STEVEN JIN

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/17/2022 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 10/19/2022 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 10/20/2022 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 10/21/2022 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 10/21/2022 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 10/26/2022 Approved HERBERT GIRON
Footing/Foundation/Slab 10/27/2022 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 1/30/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 1/30/2023 Corrections Issued HERBERT GIRON
Green Building Rough 1/30/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 1/30/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 1/30/2023 Not Ready for Inspection HERBERT GIRON
Verify Sprinkler Sign Off 1/30/2023 Not Ready for Inspection HERBERT GIRON
Wood Frame 1/30/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 2/2/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Conditional Approval HERBERT GIRON
HVAC-Rough 2/2/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 2/2/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 2/2/2023 Approved HERBERT GIRON
Shower Pan 2/2/2023 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Conditional Approval HERBERT GIRON
Shower Pan 2/6/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 2/8/2023 Corrections Issued HERBERT GIRON
Green Building Rough 2/8/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 2/8/2023 Partial Approval HERBERT GIRON
Verify Sprinkler Sign Off 2/8/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 2/10/2023 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 2/15/2023 Corrections Issued HERBERT GIRON
Deputy Drilled-In Anchors 2/17/2023 Conditional Approval RICHARD STEINBACH
BUILDING-Rough-Frame 2/21/2023 Conditional Approval HERBERT GIRON
Insulation 2/27/2023 Approved EVAN COOPER
Drywall Nailing 3/6/2023 Approved HERBERT GIRON
Final 3/6/2023 Corrections Issued HERBERT GIRON
Sewer 3/28/2023 Approved JESUS RODRIGUEZ
Underground Mechanical 3/28/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/15/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 6/15/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 6/15/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 6/15/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 6/21/2023 Approved HERBERT GIRON
ELECTRICAL-Final 6/21/2023 Approved HERBERT GIRON
Final 6/21/2023 Corrections Issued HERBERT GIRON
Green Building Final 6/21/2023 Approved HERBERT GIRON
HVAC-Final 6/21/2023 Approved HERBERT GIRON
PLUMBING-Final 6/21/2023 Corrections Issued HERBERT GIRON
Final 6/26/2023 OK to Issue CofO HERBERT GIRON
Gas Test 6/26/2023 Approved HERBERT GIRON
PLUMBING-Final 6/26/2023 Approved HERBERT GIRON
Service/Power Release 6/26/2023 Approved HERBERT GIRON