5630 E RABER ST 90042
Certificate Information: 5630 E RABER ST 90042
- Application / Permit
- 22010-20000-01463
- Plan Check / Job No.
- B22VN04366
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD (2745 SQFT) W/ATT. 2 CAR GARAGE (424 SQFT) AND COVERED FRONT PORCH (135 SQFT), COVERED PATIO (138 SQFT), (60'-6"x40'-0") W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | PETER MOSESIAN |
| Corrections Issued | 4/3/2022 | PETER MOSESIAN |
| Quality Review Completed | 4/4/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Plan Check Approved | 9/8/2022 | PETER MOSESIAN |
| Issued | 9/12/2022 | APPLICANT |
| CofO in Progress | 1/10/2024 | ROY SPAULDING |
| CofO Issued | 1/21/2024 | DEROLD HAUFF |
| Permit Finaled | 1/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/14/2022 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 5/14/2022 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 5/14/2022 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 5/14/2022 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 5/14/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 5/16/2022 | JEANETTE VONG |
| Permit | Cleared | 5/23/2022 | THAN WIN |
| Hydrant and Access approval | Cleared | 6/6/2022 | LAVEON RIDER |
| Trees in Parkway | Cleared | 6/6/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 8/22/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/23/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/25/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 11/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 11/10/2022 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/13/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/13/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 12/13/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 12/13/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 2/3/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Conditional Approval | SCOTT FINNILA |
| Shower Pan | 6/28/2023 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 6/30/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/3/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 7/3/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Shower Pan | 7/3/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/11/2023 | Corrections Issued | AMY COLIN |
| HVAC-Rough | 7/11/2023 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 7/11/2023 | Partial Inspection | AMY COLIN |
| ELECTRICAL-Rough | 7/18/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 7/18/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/18/2023 | Approved | CRAIG VAUGHAN |
| Wood Frame | 7/18/2023 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/24/2023 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/24/2023 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 7/24/2023 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/24/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/25/2023 | Corrections Issued | CRAIG VAUGHAN |
| Insulation | 7/25/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Insulation | 8/2/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 8/9/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 8/9/2023 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 8/24/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV Not Ready | ROY SPAULDING |
| Pre-Inspection | 11/14/2023 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/28/2023 | Approved | ROY SPAULDING |
| Final | 11/28/2023 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 11/28/2023 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 11/28/2023 | SGSOV Not Ready | ROY SPAULDING |
| Service/Power Release | 11/28/2023 | Not Ready for Inspection | ROY SPAULDING |
| Smoke Detectors | 11/28/2023 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Not Ready | ROY SPAULDING |
| Final | 1/9/2024 | OK to Issue CofO | ROY SPAULDING |
| Green Building Final | 1/9/2024 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | ROY SPAULDING |
| Service/Power Release | 1/9/2024 | Approved | ROY SPAULDING |