5630 E RABER ST 90042

Certificate Information: 5630 E RABER ST 90042

Application / Permit
22010-20000-01463
Plan Check / Job No.
B22VN04366
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD (2745 SQFT) W/ATT. 2 CAR GARAGE (424 SQFT) AND COVERED FRONT PORCH (135 SQFT), COVERED PATIO (138 SQFT), (60'-6"x40'-0") W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/12/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 PETER MOSESIAN
Corrections Issued 4/3/2022 PETER MOSESIAN
Quality Review Completed 4/4/2022 OMID HEDAYAT
Building Plans Picked Up 4/7/2022 APPLICANT
Plan Check Approved 9/8/2022 PETER MOSESIAN
Issued 9/12/2022 APPLICANT
CofO in Progress 1/10/2024 ROY SPAULDING
CofO Issued 1/21/2024 DEROLD HAUFF
Permit Finaled 1/21/2024 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 5/14/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 5/14/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 5/14/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 5/14/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 5/14/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/16/2022 JEANETTE VONG
Sewer availability Cleared 5/16/2022 JEANETTE VONG
Permit Cleared 5/23/2022 THAN WIN
Hydrant and Access approval Cleared 6/6/2022 LAVEON RIDER
Trees in Parkway Cleared 6/6/2022 ADALBERTO VERA
Low Impact Development Cleared 8/22/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/23/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/25/2022 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 11/9/2022 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 11/10/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 12/13/2022 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 12/13/2022 Approved CRAIG VAUGHAN
Green Building Rough 12/13/2022 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 12/13/2022 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Partial Approval CRAIG VAUGHAN
Green Building Rough 2/3/2023 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Conditional Approval SCOTT FINNILA
Shower Pan 6/28/2023 Partial Approval SCOTT FINNILA
Deputy Wood Construction 6/30/2023 Conditional Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/3/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 7/3/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 7/3/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/11/2023 Corrections Issued AMY COLIN
HVAC-Rough 7/11/2023 Corrections Issued AMY COLIN
PLUMBING-Rough 7/11/2023 Partial Inspection AMY COLIN
ELECTRICAL-Rough 7/18/2023 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 7/18/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/18/2023 Approved CRAIG VAUGHAN
Wood Frame 7/18/2023 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 7/24/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 7/24/2023 Partial Approval CRAIG VAUGHAN
HVAC-Rough 7/24/2023 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 7/24/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 7/25/2023 Corrections Issued CRAIG VAUGHAN
Insulation 7/25/2023 Not Ready for Inspection CRAIG VAUGHAN
Insulation 8/2/2023 Corrections Issued CRAIG VAUGHAN
Green Building Rough 8/9/2023 Approved CRAIG VAUGHAN
Insulation 8/9/2023 Partial Approval CRAIG VAUGHAN
Drywall Nailing 8/24/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Not Ready ROY SPAULDING
Pre-Inspection 11/14/2023 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 11/28/2023 Approved ROY SPAULDING
Final 11/28/2023 Corrections Issued ROY SPAULDING
Green Building Final 11/28/2023 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 11/28/2023 SGSOV Not Ready ROY SPAULDING
Service/Power Release 11/28/2023 Not Ready for Inspection ROY SPAULDING
Smoke Detectors 11/28/2023 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Not Ready ROY SPAULDING
Final 1/9/2024 OK to Issue CofO ROY SPAULDING
Green Building Final 1/9/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 1/9/2024 SGSOV Approved ROY SPAULDING
Service/Power Release 1/9/2024 Approved ROY SPAULDING