10531 W VALLEY SPRING LANE 91602

Certificate Information: 10531 W VALLEY SPRING LANE 91602

Application / Permit
22010-20000-01461
Plan Check / Job No.
B22VN04364
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD W/ATT 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/22/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 MAHNAZ NOURHASHEMI
Corrections Issued 4/27/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 5/3/2022 SAI KHUM
Building Plans Picked Up 6/2/2022 APPLICANT
Plan Check Approved 10/20/2022 MAHNAZ NOURHASHEMI
Issued 5/22/2023 APPLICANT
CofO in Progress 2/25/2024 KIRK SANDERS
Permit Finaled 4/2/2024 RUBEN SALAS
CofO Issued 4/2/2024 RUBEN SALAS
Permit Finaled 4/2/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/13/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/13/2022 CARLOS AGUILERA
Permit Cleared 6/13/2022 CARLOS AGUILERA
Sewer availability Cleared 6/13/2022 CARLOS AGUILERA
ZI Cleared 7/11/2022 MIGUEL GAMBOA
Trees in Parkway Cleared 7/27/2022 ADALBERTO VERA
Low Impact Development Cleared 9/1/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/2/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 9/10/2022 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/14/2023 Approved JACK KARGODORIAN
Underground Mechanical 6/14/2023 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 6/22/2023 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/18/2023 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 8/30/2023 Partial Approval JACK KARGODORIAN
HVAC-Rough 8/30/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 8/30/2023 Approved JACK KARGODORIAN
ELECTRICAL-Rough 9/11/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Shower Pan 9/11/2023 Approved CHRISTOPHE COCHRAN
Wood Frame 9/11/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/15/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 9/15/2023 Approved RYAN SALAZAR
Green Building Rough 9/15/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 9/15/2023 Approved RYAN SALAZAR
Insulation 9/21/2023 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 9/21/2023 Partial Approval JACK KARGODORIAN
Insulation 9/26/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/28/2023 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 9/29/2023 Approved JACK KARGODORIAN
Drywall Nailing 10/6/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 1/16/2024 Corrections Issued KIRK SANDERS
HVAC-Final 1/16/2024 Corrections Issued KIRK SANDERS
PLUMBING-Final 1/16/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 2/16/2024 Approved KIRK SANDERS
Final 2/16/2024 Corrections Issued KIRK SANDERS
Green Building Final 2/16/2024 Approved KIRK SANDERS
HVAC-Final 2/16/2024 Approved KIRK SANDERS
PLUMBING-Final 2/16/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 2/16/2024 SGSOV Approved KIRK SANDERS
Service/Power Release 2/16/2024 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 2/16/2024 Approved KIRK SANDERS
ELECTRICAL-Final 2/21/2024 Not Ready for Inspection KIRK SANDERS
HVAC-Final 2/21/2024 Approved KIRK SANDERS
Final 2/23/2024 OK to Issue CofO KIRK SANDERS
Service/Power Release 2/23/2024 Approved KIRK SANDERS