10531 W VALLEY SPRING LANE 91602
Certificate Information: 10531 W VALLEY SPRING LANE 91602
- Application / Permit
- 22010-20000-01461
- Plan Check / Job No.
- B22VN04364
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD W/ATT 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/22/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 4/27/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 5/3/2022 | SAI KHUM |
| Building Plans Picked Up | 6/2/2022 | APPLICANT |
| Plan Check Approved | 10/20/2022 | MAHNAZ NOURHASHEMI |
| Issued | 5/22/2023 | APPLICANT |
| CofO in Progress | 2/25/2024 | KIRK SANDERS |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
| CofO Issued | 4/2/2024 | RUBEN SALAS |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | CARLOS AGUILERA |
| Permit | Cleared | 6/13/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/13/2022 | CARLOS AGUILERA |
| ZI | Cleared | 7/11/2022 | MIGUEL GAMBOA |
| Trees in Parkway | Cleared | 7/27/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 9/1/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/2/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 9/10/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/14/2023 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 6/14/2023 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 6/22/2023 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2023 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 8/30/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/30/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 9/11/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Shower Pan | 9/11/2023 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 9/11/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/15/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/15/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/15/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 9/15/2023 | Approved | RYAN SALAZAR |
| Insulation | 9/21/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 9/21/2023 | Partial Approval | JACK KARGODORIAN |
| Insulation | 9/26/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/28/2023 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 9/29/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 10/6/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 1/16/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 1/16/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 1/16/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 2/16/2024 | Approved | KIRK SANDERS |
| Final | 2/16/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 2/16/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 2/16/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 2/16/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/16/2024 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 2/16/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 2/16/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 2/21/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 2/21/2024 | Approved | KIRK SANDERS |
| Final | 2/23/2024 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 2/23/2024 | Approved | KIRK SANDERS |