7040 N WILLIS AVE 91405
Certificate Information: 7040 N WILLIS AVE 91405
- Application / Permit
- 22010-20000-01450
- Plan Check / Job No.
- B22VN04304
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30'-6" X 20'-6" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | SELLA BENYAMIN |
| Corrections Issued | 4/5/2022 | SELLA BENYAMIN |
| Quality Review Completed | 4/7/2022 | STEVEN KIM |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| Applicant returned to address corrections | 7/7/2022 | SELLA BENYAMIN |
| Plan Check Approved | 8/4/2022 | SELLA BENYAMIN |
| Issued | 8/26/2022 | APPLICANT |
| CofO in Progress | 1/23/2023 | RYAN SALAZAR |
| CofO Issued | 2/13/2023 | MICHAEL SMITH |
| Permit Finaled | 2/13/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/24/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 6/6/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/8/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/21/2022 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 9/27/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Partial Approval | RICHARD DOCKUS |
| Rough-Elec/Plmb/HVAC | 11/4/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 11/7/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 11/10/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 11/10/2022 | Approved | RICHARD DOCKUS |
| Insulation | 11/10/2022 | Approved | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 11/10/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 11/14/2022 | Approved | RICHARD DOCKUS |
| Gas Test | 11/22/2022 | Approved | RYAN SALAZAR |
| Underground Mechanical | 11/22/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 11/29/2022 | Approved | JOHN COLEMAN |
| Underground Mechanical | 11/29/2022 | Approved | JOHN COLEMAN |
| Sewer | 12/9/2022 | Approved | RYAN SALAZAR |
| Final | 1/12/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 1/12/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/12/2023 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 1/12/2023 | Not Required | RYAN SALAZAR |
| Smoke Detectors | 1/12/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 1/23/2023 | Approved | RYAN SALAZAR |
| Final | 1/23/2023 | OK to Issue CofO | RYAN SALAZAR |
| HVAC-Final | 1/23/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 1/23/2023 | Approved | RYAN SALAZAR |