7040 N WILLIS AVE 91405

Certificate Information: 7040 N WILLIS AVE 91405

Application / Permit
22010-20000-01450
Plan Check / Job No.
B22VN04304
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30'-6" X 20'-6" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 8/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2022 APPLICANT
Assigned to Plan Check Engineer 3/31/2022 SELLA BENYAMIN
Corrections Issued 4/5/2022 SELLA BENYAMIN
Quality Review Completed 4/7/2022 STEVEN KIM
Building Plans Picked Up 4/11/2022 APPLICANT
Applicant returned to address corrections 7/7/2022 SELLA BENYAMIN
Plan Check Approved 8/4/2022 SELLA BENYAMIN
Issued 8/26/2022 APPLICANT
CofO in Progress 1/23/2023 RYAN SALAZAR
CofO Issued 2/13/2023 MICHAEL SMITH
Permit Finaled 2/13/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/19/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/24/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/24/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 6/6/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/8/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/21/2022 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 9/27/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 10/20/2022 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Partial Approval RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 11/4/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 11/7/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 11/10/2022 Approved RICHARD DOCKUS
Green Building Rough 11/10/2022 Approved RICHARD DOCKUS
Insulation 11/10/2022 Approved RICHARD DOCKUS
Verify Sprinkler Sign Off 11/10/2022 Approved RICHARD DOCKUS
Drywall Nailing 11/14/2022 Approved RICHARD DOCKUS
Gas Test 11/22/2022 Approved RYAN SALAZAR
Underground Mechanical 11/22/2022 Approved RYAN SALAZAR
ELECTRICAL-Rough 11/29/2022 Approved JOHN COLEMAN
Underground Mechanical 11/29/2022 Approved JOHN COLEMAN
Sewer 12/9/2022 Approved RYAN SALAZAR
Final 1/12/2023 Not Ready for Inspection RYAN SALAZAR
Green Building Final 1/12/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 1/12/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 1/12/2023 Not Required RYAN SALAZAR
Smoke Detectors 1/12/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 1/23/2023 Approved RYAN SALAZAR
Final 1/23/2023 OK to Issue CofO RYAN SALAZAR
HVAC-Final 1/23/2023 Approved RYAN SALAZAR
PLUMBING-Final 1/23/2023 Approved RYAN SALAZAR