9315 S WADSWORTH AVE 90002

Certificate Information: 9315 S WADSWORTH AVE 90002

Application / Permit
22010-20000-01402
Plan Check / Job No.
B22VN04176
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 11'-11" X 28'-1" FACTORY BUILT ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) PER STANDARD PLAN 1
Permit Issued
Issued on 5/25/2022
Issuing Office
Current Status
CofO Issued on 6/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/21/2022 SELLA BENYAMIN
Corrections Issued 3/21/2022 SELLA BENYAMIN
Applicant returned to address corrections 4/4/2022 SELLA BENYAMIN
Applicant returned to address corrections 4/20/2022 SELLA BENYAMIN
Plan Check Approved 5/20/2022 SELLA BENYAMIN
Issued 5/25/2022 APPLICANT
CofO in Progress 5/30/2023 JOHN KLARIN
CofO in Progress 6/9/2023 JOHN KLARIN
CofO in Progress 6/14/2023 ANSON MAGLASANG
Permit Finaled 6/23/2023 ANSON MAGLASANG
CofO Issued 6/23/2023 ANSON MAGLASANG
Permit Finaled 6/23/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/25/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 3/25/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 3/25/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 4/5/2022 CHRISTOPHER ROCHA
Construction near power lines Cleared 5/13/2022 RIDWAN HARDY

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B 150 E 57TH ST      LOS ANGELES, CA 90011
Engineer Sveiven,, Shane; Lic. No.: C89133 1909 S ALMA STREET      SAN PEDRO, CA 90731

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/19/2022 Approved JOHN KLARIN
Sewer 8/19/2022 Approved JOHN KLARIN
Underground Mechanical 8/19/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 9/29/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 9/29/2022 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 9/29/2022 Approved ALIZAH MAYAGOITIA
HVAC-Rough 12/5/2022 Corrections Issued JOHN KLARIN
Final 12/13/2022 Not Ready for Inspection JOHN KLARIN
Footing/Foundation/Slab 12/13/2022 Approved JOHN KLARIN
Green Building Final 12/13/2022 Not Ready for Inspection JOHN KLARIN
HVAC-Rough 12/13/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Not Ready JOHN KLARIN
Service/Power Release 12/13/2022 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 12/13/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 1/19/2023 Not Ready for Inspection JOHN KLARIN
Service/Power Release 1/19/2023 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 2/13/2023 Approved JOHN KLARIN
Final 2/13/2023 Corrections Issued JOHN KLARIN
Green Building Final 2/13/2023 Corrections Issued JOHN KLARIN
HVAC-Final 2/13/2023 Corrections Issued JOHN KLARIN
PLUMBING-Final 2/13/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 2/13/2023 SGSOV Approved JOHN KLARIN
Service/Power Release 2/13/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 2/13/2023 Approved JOHN KLARIN
Final 4/4/2023 Corrections Issued JOHN KLARIN
Green Building Final 4/4/2023 No Access for Inspection JOHN KLARIN
HVAC-Final 4/4/2023 No Access for Inspection JOHN KLARIN
Service/Power Release 4/4/2023 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 5/26/2023 Approved JOHN KLARIN
Final 5/26/2023 OK to Issue CofO JOHN KLARIN
Green Building Final 5/26/2023 Approved JOHN KLARIN
HVAC-Final 5/26/2023 Approved JOHN KLARIN
Service/Power Release 5/26/2023 Approved JOHN KLARIN