4057 1/2 E SEQUOIA ST 90039

Certificate Information: 4057 1/2 E SEQUOIA ST 90039

Application / Permit
22010-20000-01392
Plan Check / Job No.
B22VN04115
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW Detached ADU checked per LAMC 12.22 A.33(c) and (d) and STRUCTURAL PER WFPP
Permit Issued
Issued on 1/19/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 SUNMIN LEE
Corrections Issued 4/19/2022 SUNMIN LEE
Quality Review Completed 4/28/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 4/29/2022 APPLICANT
Applicant returned to address corrections 12/27/2022 SUNMIN LEE
Plan Check Approved 1/19/2023 SUNMIN LEE
Issued 1/19/2023 APPLICANT
CofO in Progress 2/21/2024 COREY HUPP
Permit Finaled 3/27/2024 DANIEL SANCHEZ
CofO Issued 3/27/2024 DANIEL SANCHEZ
Permit Finaled 3/27/2024 DANIEL SANCHEZ

Permit Application Clearance Information

ZI Cleared 10/12/2022 MIGUEL GAMBOA
Address approval Cleared 10/19/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/26/2022 STEVE MELGAR
Sewer availability Cleared 10/26/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 12/19/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/11/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 4/11/2023 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 4/17/2023 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 4/17/2023 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 4/19/2023 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Partial Approval COREY HUPP
Green Building Rough 5/24/2023 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 5/24/2023 Approved COREY HUPP
BUILDING-Rough-Frame 6/14/2023 Partial Approval COREY HUPP
Green Building Rough 6/14/2023 Not Ready for Inspection COREY HUPP
Rough-Elec/Plmb/HVAC 6/14/2023 Approved COREY HUPP
Verify Sprinkler Sign Off 6/14/2023 Approved COREY HUPP
BUILDING-Rough-Frame 6/28/2023 Approved COREY HUPP
ELECTRICAL-Rough 6/28/2023 Approved COREY HUPP
Green Building Rough 6/28/2023 Approved COREY HUPP
Interior/Exterior Lathing 6/28/2023 Partial Approval COREY HUPP
Insulation 8/1/2023 Approved COREY HUPP
Underground Mechanical 8/3/2023 Partial Approval COREY HUPP
Underground Mechanical 8/7/2023 Approved COREY HUPP
Drywall Nailing 8/15/2023 Approved COREY HUPP
Shower Pan 8/29/2023 Approved COREY HUPP
Interior/Exterior Lathing 8/31/2023 Approved PTOLEMY HILL
Gas Test 9/27/2023 Approved COREY HUPP
Final 11/1/2023 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 11/1/2023 Approved COREY HUPP
Green Building Final 11/1/2023 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 11/1/2023 SGSOV Approved COREY HUPP
Service/Power Release 11/1/2023 Not Ready for Inspection COREY HUPP
Smoke Detectors 11/1/2023 Approved COREY HUPP
Final 11/14/2023 Partial Inspection COREY HUPP
Green Building Final 11/14/2023 Approved COREY HUPP
Service/Power Release 11/14/2023 Corrections Issued COREY HUPP
Final 2/16/2024 OK to Issue CofO COREY HUPP
Service/Power Release 2/16/2024 Approved COREY HUPP
Pre-Inspection 2/29/2024 Approved COREY HUPP