404 N FORMOSA AVE 90036
Certificate Information: 404 N FORMOSA AVE 90036
- Application / Permit
- 22010-20000-01387
- Plan Check / Job No.
- B22VN04102
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- NEW DETACHED 20' x 20' CARPORT
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | SEAN SHAHMIRI |
| Corrections Issued | 4/4/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 4/8/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/13/2022 | APPLICANT |
| Applicant returned to address corrections | 8/16/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 8/29/2022 | SEAN SHAHMIRI |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 8/15/2025 | JOSE MACIAS |
| Permit Finaled | 8/16/2025 | DEROLD HAUFF |
| CofO Issued | 8/16/2025 | DEROLD HAUFF |
| Permit Finaled | 8/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 5/11/2022 | CINDY JOSSELYN |
| Construction within easement | Cleared | 6/14/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 7/7/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/5/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 123 N VALENCIA ST ALHAMBRA, CA 91801 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 2/16/2023 | Approved | MICHAEL LEWIS |
| Deputy Shotcrete | 3/17/2023 | Conditional Approval | MICHAEL LEWIS |
| Deputy Shotcrete | 3/23/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Shotcrete | 3/24/2023 | Conditional Approval | MICHAEL LEWIS |
| Deputy Other (see comments) | 5/23/2023 | No Access for Inspection | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 6/18/2024 | Partial Approval | AMIR NAZARIAN |
| Footing/Foundation/Slab | 6/18/2024 | Partial Inspection | AMIR NAZARIAN |
| METHANE-Barrier | 6/18/2024 | Partial Inspection | AMIR NAZARIAN |
| METHANE-Subgrade | 6/18/2024 | Partial Inspection | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Approved | AMIR NAZARIAN |
| Footing/Foundation/Slab | 6/26/2024 | Approved | AMIR NAZARIAN |
| METHANE-Barrier | 6/26/2024 | Approved | AMIR NAZARIAN |
| METHANE-Final | 6/26/2024 | Approved | AMIR NAZARIAN |
| METHANE-Subgrade | 6/26/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 7/25/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 8/1/2024 | Corrections Issued | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 9/20/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 9/20/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 9/26/2024 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 3/13/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 8/5/2025 | Approved | JOSE MACIAS |
| Final | 8/5/2025 | No Access for Inspection | JOSE MACIAS |
| HVAC-Final | 8/5/2025 | Approved | JOSE MACIAS |
| PLUMBING-Final | 8/5/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 8/5/2025 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 8/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 8/5/2025 | Approved | JOSE MACIAS |
| Final | 8/8/2025 | Not Ready for Inspection | JOSE MACIAS |
| Service/Power Release | 8/8/2025 | Not Ready for Inspection | JOSE MACIAS |
| Final | 8/12/2025 | Not Ready for Inspection | JOSE MACIAS |
| Service/Power Release | 8/12/2025 | Not Ready for Inspection | JOSE MACIAS |
| Final | 8/13/2025 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 8/13/2025 | Approved | JOSE MACIAS |
| Service/Power Release | 8/14/2025 | Approved | JOSE MACIAS |