6709 1/2 N ORION AVE 91406

Certificate Information: 6709 1/2 N ORION AVE 91406

Application / Permit
22010-20000-01384
Plan Check / Job No.
B22VN04101
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 31'-6" x 40'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER WFPP.
Permit Issued
Issued on 4/27/2022
Issuing Office
Current Status
CofO Issued on 1/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2022 APPLICANT
Assigned to Plan Check Engineer 3/25/2022 SARKIS HARABEDIAN
Corrections Issued 3/26/2022 SARKIS HARABEDIAN
Plan Check Approved 4/27/2022 SARKIS HARABEDIAN
Issued 4/27/2022 APPLICANT
Building Plans Picked Up 4/28/2022 APPLICANT
CofO in Progress 12/28/2022 RYAN SALAZAR
CofO Issued 1/10/2023 MICHAEL SMITH
Permit Finaled 1/10/2023 MICHAEL SMITH

Permit Application Clearance Information

CPC Cleared 3/30/2022 LAUREN PADICK
ZI Cleared 3/30/2022 LAUREN PADICK
Address approval Cleared 3/31/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/1/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 4/1/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 4/14/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 4/15/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/25/2022 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 5/31/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 6/9/2022 Partial Approval DEANDRE HOFFMAN
BUILDING-Rough-Frame 6/10/2022 Partial Approval RICHARD DOCKUS
Insulation 6/10/2022 Not Ready for Inspection RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 6/16/2022 Partial Approval RICHARD DOCKUS
Insulation 6/16/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/5/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 7/11/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 7/15/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 7/28/2022 Approved JACK KARGODORIAN
HVAC-Rough 7/28/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 8/3/2022 Approved RICHARD DOCKUS
Green Building Rough 8/3/2022 Approved RICHARD DOCKUS
MERV13>=Rough 8/3/2022 Approved RICHARD DOCKUS
Verify Sprinkler Sign Off 8/3/2022 Approved RICHARD DOCKUS
Insulation 8/10/2022 Approved JACK KARGODORIAN
Drywall Nailing 8/18/2022 Approved DEANDRE HOFFMAN
Gas Test 8/23/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 8/23/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 11/2/2022 Approved RICHARD DOCKUS
Sewer 11/2/2022 Approved RICHARD DOCKUS
Underground Mechanical 11/2/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 12/7/2022 Approved RYAN SALAZAR
HVAC-Final 12/7/2022 Approved RYAN SALAZAR
PLUMBING-Final 12/7/2022 Corrections Issued RYAN SALAZAR
Final 12/19/2022 Corrections Issued RYAN SALAZAR
Green Building Final 12/19/2022 Approved RYAN SALAZAR
MERV13>=Final 12/19/2022 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Approved RYAN SALAZAR
Service/Power Release 12/19/2022 Not Required RYAN SALAZAR
Smoke Detectors 12/19/2022 Approved RYAN SALAZAR
Final 12/28/2022 OK to Issue CofO RYAN SALAZAR