20309 W STAGG ST 91306
Certificate Information: 20309 W STAGG ST 91306
- Application / Permit
- 22010-20000-01383
- Plan Check / Job No.
- B22VN04079
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 20' X 23' 2-CAR GARAGE TO REAR OF (E) SFD. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 2/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 3/27/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/11/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 4/18/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 4/19/2022 | APPLICANT |
| Issued | 4/26/2022 | APPLICANT |
| Permit Closed-Status Void | 1/17/2023 | ALEXANDER HANDY |
| Re-Activate Permit | 2/16/2023 | ALEXANDER HANDY |
| CofO in Progress | 2/16/2023 | ALEXANDER HANDY |
| Permit Finaled | 2/16/2023 | MICHAEL SMITH |
| CofO Issued | 2/16/2023 | MICHAEL SMITH |
| Permit Finaled | 2/16/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/6/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2022 | JOSE DUARTE-DIAZ |
| "T" removal | Cleared | 4/11/2022 | DANG NGUYEN |
Contact Information
| Contractor | Isaac Construction; Lic. No.: 1058504-B | 4228 CANOGA DRIVE WOODLAND HILLS, CA 91364 |
| Engineer | Isaac,, Raymond; Lic. No.: C84605 | 4228 CANOGA DR WOODLAND HILLS, CA 91364 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/16/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 5/16/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 11/3/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Approved | STEVEN BACK |
| Final | 11/21/2022 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 11/21/2022 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 11/21/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/1/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | STEVEN BACK |
| Final | 12/5/2022 | Not Ready for Inspection | STEVEN BACK |
| Final | 1/17/2023 | Partial Approval | ALEXANDER HANDY |
| Final | 2/16/2023 | OK to Issue CofO | ALEXANDER HANDY |