6803 N ALDEA AVE 91406
Certificate Information: 6803 N ALDEA AVE 91406
- Application / Permit
- 22010-20000-01380
- Plan Check / Job No.
- B22VN04037
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 30' X 66' 6" DETACHED 2-CAR GARAGE AND STORAGE BUILDING. ALL WORK DONE PER ENGINEERING. COMPLY WITH DEPARTMENT ORDER effective date 11/30/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 3/29/2023
- Issuing Office
- Current Status
- CofO Issued on 11/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 3/26/2022 | DANIEL ABRAMYAN |
| Building Plans Picked Up | 4/1/2022 | APPLICANT |
| Plan Check Approved | 3/20/2023 | GURUNATH NESARAJAH |
| Issued | 3/29/2023 | APPLICANT |
| CofO in Progress | 9/4/2024 | MICKEY YAMASHITA |
| CofO Issued | 11/18/2024 | DAVID JAMES |
| Permit Finaled | 11/18/2024 | DAVID JAMES |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/2/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 1/20/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 2/13/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2023 | Approved | MICKEY YAMASHITA |
| Special/Order Compliance | 7/12/2023 | Not Ready for Inspection | MICKEY YAMASHITA |
| Pre-Inspection | 7/26/2023 | Corrections Issued | MICKEY YAMASHITA |
| Excavation/Setback/Form/Re-Bar | 8/7/2023 | Corrections Issued | MICKEY YAMASHITA |
| Excavation/Setback/Form/Re-Bar | 8/24/2023 | Approved | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 8/24/2023 | Approved | MICKEY YAMASHITA |
| Green Building Rough | 8/24/2023 | Partial Approval | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2023 | Approved | MICKEY YAMASHITA |
| Wood Frame | 8/28/2023 | Conditional Approval | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 9/19/2023 | Approved | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 9/19/2023 | Approved | MICKEY YAMASHITA |
| Green Building Rough | 9/19/2023 | Approved | MICKEY YAMASHITA |
| Interior/Exterior Lathing | 9/25/2023 | Conditional Approval | MICKEY YAMASHITA |
| Drywall Nailing | 10/3/2023 | Approved | MICKEY YAMASHITA |
| Pre-Inspection | 10/31/2023 | Approved | MICKEY YAMASHITA |
| Drywall Nailing | 1/2/2024 | Approved | MICKEY YAMASHITA |
| ELECTRICAL-Final | 7/18/2024 | Conditional Approval | MICKEY YAMASHITA |
| Final | 7/18/2024 | Not Ready for Inspection | MICKEY YAMASHITA |
| Green Building Final | 7/18/2024 | Approved | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | MICKEY YAMASHITA |
| Service/Power Release | 7/18/2024 | Conditional Approval | MICKEY YAMASHITA |
| Smoke Detectors | 7/18/2024 | Approved | MICKEY YAMASHITA |
| Final | 9/4/2024 | OK to Issue CofO | MICKEY YAMASHITA |
| Service/Power Release | 9/4/2024 | Approved | MICKEY YAMASHITA |