17205 W SATICOY ST 91406
Certificate Information: 17205 W SATICOY ST 91406
- Application / Permit
- 22010-20000-01379
- Plan Check / Job No.
- B22VN04031
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO DETACHED GARAGE AND CONVERT TO ADU.
- Permit Issued
- Issued on 1/9/2024
- Issuing Office
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2022 | JOE VO |
| Corrections Issued | 5/4/2022 | JOE VO |
| Plan Check Approved | 1/8/2024 | JOE VO |
| Issued | 1/9/2024 | APPLICANT |
| CofO in Progress | 5/30/2024 | SALVADOR MARTINEZ |
| Permit Finaled | 7/3/2024 | RUBEN SALAS |
| CofO Issued | 7/3/2024 | RUBEN SALAS |
| Permit Finaled | 7/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/6/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 5/6/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2022 | ROMAN GUTIERREZ |
| Miscellaneous | Cleared | 1/5/2024 | MANUEL TEJADA |
| Sewer availability | Cleared | 1/8/2024 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: NA4808 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/12/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 1/12/2024 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 1/12/2024 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 1/17/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 1/17/2024 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 2/2/2024 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 2/2/2024 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 2/7/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 2/7/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 2/7/2024 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/9/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 2/9/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 2/9/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 2/9/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 2/16/2024 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 2/16/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 2/16/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Shower Pan | 2/16/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Drywall Nailing | 2/21/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 2/29/2024 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 2/29/2024 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 3/12/2024 | Partial Approval | SALVADOR MARTINEZ |
| Sewer | 3/13/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 3/13/2024 | Partial Approval | SALVADOR MARTINEZ |
| Sewer | 3/14/2024 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 4/12/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 4/12/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 5/2/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/23/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 5/23/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 5/23/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 5/23/2024 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 5/23/2024 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 5/23/2024 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Final | 5/23/2024 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 5/23/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 5/28/2024 | OK for TCO | SALVADOR MARTINEZ |
| Final | 5/30/2024 | OK to Issue CofO | SALVADOR MARTINEZ |
| Service/Power Release | 5/30/2024 | Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 5/30/2024 | Approved | SALVADOR MARTINEZ |