13748 N KISMET AVE 91342
Certificate Information: 13748 N KISMET AVE 91342
- Application / Permit
- 22010-20000-01378
- Plan Check / Job No.
- B22VN04030
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO DETACHED ADU PER STATE LAW
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- CofO Issued on 1/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | CARLOS MONTES |
| Corrections Issued | 3/17/2022 | CARLOS MONTES |
| Plan Check Approved | 4/21/2022 | CARLOS MONTES |
| Issued | 4/21/2022 | APPLICANT |
| CofO in Progress | 1/23/2023 | ROBERT GOLD |
| Permit Finaled | 1/24/2023 | MICHAEL SMITH |
| CofO Issued | 1/24/2023 | MICHAEL SMITH |
| Permit Finaled | 1/24/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/6/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/6/2022 | Partial Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/19/2022 | Approved | ARAM AVEDISIAN |
| Sewer | 10/19/2022 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/3/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/15/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/15/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Rough | 11/15/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/18/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/18/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/18/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/18/2022 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 11/23/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 11/30/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/30/2022 | Partial Approval | ARAM AVEDISIAN |
| Special/Order Compliance | 11/30/2022 | Approved | ARAM AVEDISIAN |
| Final | 1/18/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 1/18/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/18/2023 | SGSOV Not Required | ARAM AVEDISIAN |
| Smoke Detectors | 1/18/2023 | Approved | ARAM AVEDISIAN |
| Final | 1/23/2023 | OK to Issue CofO | ROBERT GOLD |