23222 W CANZONET ST 91367

Certificate Information: 23222 W CANZONET ST 91367

Application / Permit
22010-20000-01365
Plan Check / Job No.
B22VN04004
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW 21'-4" X 37'-6" ACCESSORY LIVING QUARTERS WITH ATTACHED PATIO COVER AND FULL BATHROOM. WORK PER ENGINEER. AUTOMATIC FIRE SPRINKLER SYSTEM REQUIRED.
Permit Issued
Issued on 7/19/2022
Issuing Office
Current Status
CofO Issued on 7/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/21/2022 ROSENDO MEDINA
Corrections Issued 3/21/2022 ROSENDO MEDINA
Applicant returned to address corrections 7/8/2022 ROSENDO MEDINA
Plan Check Approved 7/12/2022 ROSENDO MEDINA
Issued 7/19/2022 APPLICANT
Building Plans Picked Up 7/21/2022 APPLICANT
CofO in Progress 7/26/2023 TROY SANDERS
Permit Finaled 7/31/2023 JOHN JANSON
CofO Issued 7/31/2023 JOHN JANSON
Permit Finaled 7/31/2023 JOHN JANSON

Permit Application Clearance Information

GPI Written Notices Cleared 3/23/2022 ROSENDO MEDINA
Grading Pre-Inspection Cleared 3/23/2022 ROSENDO MEDINA
Tract Map conditions Cleared 3/24/2022 MIGUEL GAMBOA
ZA Case Cleared 3/24/2022 MIGUEL GAMBOA
ZI Cleared 3/24/2022 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 3/25/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 4/26/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 4/27/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Wrap Development Group Inc; Lic. No.: 1029313-B 2828 COCHRAN STREET #414      SIMI VALLEY, CA 93065
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/28/2022 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 11/8/2022 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Partial Approval TROY SANDERS
PLUMBING-Rough 1/13/2023 Partial Approval TROY SANDERS
Gas Test 1/19/2023 Approved TROY SANDERS
HVAC-Rough 1/19/2023 Approved TROY SANDERS
PLUMBING-Rough 1/19/2023 Approved TROY SANDERS
Sewer 1/19/2023 Approved TROY SANDERS
Shower Pan 1/19/2023 Approved TROY SANDERS
Special/Order Compliance 1/19/2023 Partial Inspection MORRIS JACKSON
BUILDING-Rough-Frame 1/25/2023 Conditional Approval TROY SANDERS
ELECTRICAL-Rough 1/25/2023 Approved TROY SANDERS
Green Building Rough 1/25/2023 Not Ready for Inspection TROY SANDERS
Verify Sprinkler Sign Off 1/25/2023 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 1/30/2023 Approved JUSTIN HAWLEY
Green Building Rough 1/30/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 1/30/2023 Approved JUSTIN HAWLEY
Verify Sprinkler Sign Off 1/30/2023 Approved JUSTIN HAWLEY
Insulation 2/8/2023 Approved TROY SANDERS
Drywall Nailing 2/21/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Not Ready HORACE FULTZ
Final 7/11/2023 Not Ready for Inspection TROY SANDERS
Green Building Final 7/11/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/11/2023 SGSOV Approved TROY SANDERS
Service/Power Release 7/11/2023 Approved TROY SANDERS
Smoke Detectors 7/11/2023 Approved TROY SANDERS
Final 7/26/2023 OK to Issue CofO TROY SANDERS